Tellurian provides update on Driftwood LNG construction

US LNG terminal developer Tellurian released the latest construction update for its Driftwood LNG terminal in Louisiana, while it still works on securing financing for the project worth about $14.5 billion.

Tellurian issued a limited notice to proceed to compatriot engineering and construction giant Bechtel in March 2022.

Under the first phase, Tellurian aims to build two LNG plants near Lake Charles with an export capacity of up to 11 mtpa.

The firm said in an update in August 2023 that Bechtel had completed piling work for the first plant and also concrete pouring for all plant one compressor foundations.

According to the December 2023 construction report filed with the US FERC, the Driftwood project has continued construction activities including site preparation, excavation and backfill, offloading of concrete pile shipments, and pile driving activities.

The project continued maintenance of site roads and drainage effort, continued concrete pile installation in tank 1, completed concrete pile installation in tank 2, completed concrete pile shipment for LNTP scope, and completed MOF preservation activities.

In January, the project will continue maintenance of site roads and drainage efforts, and will continue concrete pile installation in tank 1.

Tellurian provides update on Driftwood LNG construction
Image: Tellurian

Tellurian recently appointed a financial adviser to assist with shaping commercial structures as well as balance sheet management.

Tellurian’s co-founder Martin Houston and new chairman of the board revealed this in a letter sent to shareholders on December 28.

In December, the company appointed Houston as the chairman replacing Charif Souki, who has left the Driftwood LNG terminal developer.

- Advertisements -

Most Popular

NYK’s LNG carrier fleet expands to 91 vessels

Japan’s shipping giant NYK said its fleet of operational liquefied natural gas (LNG) carriers rose to 91 vessels by...

Sempra says ECA LNG export project more than 80 percent complete

US LNG exporter Sempra said that construction of the first phase of its Energía Costa Azul LNG export project...

Sempra updates on Port Arthur LNG work

US LNG exporter Sempra and compatriot engineering and construction firm Bechtel are moving forward with construction on the first...

More News Like This

Tellurian’s net loss widens in Q1, Driftwood LNG talks continue

US LNG firm Tellurian reported a widening first-quarter loss on Thursday, as it continues to work to secure financing...

Tellurian explores sale options, makes leadership changes

US LNG firm Tellurian, the developer of the Driftwood LNG export project in Louisiana, has made new changes to...

Tellurian expects to take FID on two Driftwood LNG plants in 2024

US LNG firm Tellurian said on Monday it expects to take a final investment decision in 2024 to build...

Tellurian reports $166.2 million net loss in 2023

US LNG firm Tellurian reported a net loss of $166.2 million in 2023, as it continues to work on...