FERC suspends Kenai LNG environmental review

The US FERC is temporarily suspending an environmental assessment of a proposal to bring the closed Kenai LNG plant in Alaska back online as an import facility.

FERC said on April 8 it would suspend the environmental review for the project until the U.S. Pipeline and Hazardous Materials Safety Administration performs an “equivalency determination” related to a proposed vaporizer at the facility.

Marathon’s unit Trans-Foreland Pipeline proposes to the PHMSA to have the trim vaporizer within the LNG storage tank impoundment area.

FERC previously expected to issue an assessment for the Kenai import project on April 24. After that, the agency planned to make a decision by July 23.

The agency will now issue a revised schedule for the project once it can review the PHMSA documents, it said.

FERC said that this was not a suspension of its review of Trans-Foreland’s project.

“Staff will continue to process Trans-Foreland’s proposal to the extent possible based upon the information it has filed to date,” the agency said.

The fuel would go to an adjacent refinery

Trans Foreland filed an application with FERC back in March 2019.

It plans to make modifications to bring parts of Kenai LNG out of its current “warm idle status” to allow for imports.

The Kenai LNG cool down project would allow the plant to provide up to 7 million standard cubic feet per day of gas.

The fuel would be supplied to Trans-Foreland’s affiliated Kenai refinery adjacent to the LNG plant.

Trans-Foreland plans to add a new electric-driven boil-off-gas booster compressor unit, trim vaporizers and additional LNG transfer system valves.

ConocoPhillips sold the Kenai facility to a unit of Andeavor in February 2018.

Marathon completed its purchase of Andeavor in October 2018.

The Kenai plant was the only LNG export facility in North America for 47 years.

This was until Cheniere’s Sabine Pass export terminal in Louisiana entered service in February 2016.

The Kenai facility has not exported LNG cargoes since the fourth quarter of 2015.

Most Popular

Knutsen’s LNG FSU ready for Honduras job

Knutsen’s 2004-built LNG carrier, Bilbao Knutsen, has been converted into a floating storage unit, and the vessel is ready to start serving an LNG-to-power project in Honduras.

LNG shipping rates continue to drop

Spot LNG freight shipping rates in both basins and European prices continued to decrease this week.

Energy Transfer, EIG’s MidOcean to jointly develop Lake Charles LNG project

MidOcean Energy, the LNG unit of US-based energy investor EIG, has signed a heads of agreement with Energy Transfer to jointly develop the latter's Lake Charles LNG export facility in Louisiana.

More News Like This

Cheniere progresses commissioning of second Corpus Christi expansion train

US LNG exporting giant Cheniere is moving forward with commissioning activities at the second train of the Corpus Christi Stage 3 expansion project in Texas following the substantial completion of the first unit.

Freeport LNG to launch Noble gas project

Freeport LNG, the operator of the 15 mtpa liquefaction plant in Texas, has won an extension of time from the US FERC to construct and place into service its Noble gas project. The LNG terminal operator plans to launch the project this month.

Venture Global LNG gets Calcasieu Pass approval from FERC

US LNG exporter Venture Global LNG has received approval from the US FERC to launch operations of its entire Calcasieu Pass LNG terminal in Louisiana.

US FERC issues draft supplemental EIS for Glenfarne’s Texas LNG project

The US Federal Energy Regulatory Commission (FERC) has released a draft supplemental environmental impact statement for Glenfarne's planned 4 mtpa Texas LNG export project in the port of Brownsville. The regulator said that it continues to conclude that approval of the project would result in "less than significant impacts."