Hudong says second LNG carrier for CSSC Shipping wraps up sea trials

China’s Hudong-Zhonghua is moving forward with works on the second LNG carrier it is building for CSSC Shipping, the financial leasing unit of China State Shipbuilding Corporation.

Hudong, also part of CSSC, said the 174,000-cbm Gui Ying has completed its sea trials and returned to its yard on Changxing Island, Shanghai last week. The trials took 5 days.

The LNG carrier will later this year head out to complete its gas trials. According to the current schedule, Hudong should deliver Gui Ying in February 2022.

Its sister vessel Mu Lan has recently completed gas trials and Hudong should deliver this ship next month.

In addition to these vessels, the Chinese yard also signed another contract with CSSC Shipping in July for the third LNG carrier.

Part of Hudong’s fourth-generation Changxing series, all the LNG carriers will feature WinGD’s X-DF dual-fuel engines and GTT’s NO96 L03+ containment system.

They will be 295 meters long and 45 meters wide.

Most Popular

BP achieves first gas at Tortue FLNG project

According to a joint statement by the energy ministries of Senegal and Mauritania, Petrosen, and SMH, gas production from...

Norway’s Equinor shuts Hammerfest LNG terminal

Gassco data showed on Thursday that Hammerfest LNG will be offline until January 9, 2025. LNG Prime invited Equinor to...

Top 5 LNG Prime articles of 2024

LNG Prime wishes all our readers and partners a happy New Year 2025! Here are the top 5 most...

More News Like This

LNG carrier orders climb in 2024

The data shows there were at least 78 orders for large LNG carriers in 2024. This compares to about 68...

Hudong-Zhonghua launches two LNG tankers

Chinese shipbuilder Hudong-Zhonghua has launched two 174,000-cbm liquefied natural gas (LNG) carriers. According to a statement by Hudong-Zhonghua, the launching...

Hudong-Zhonghua delivers 8th LNG carrier in 2024

Last year, Hudong-Zhonghua delivered a record six LNG carriers. Earlier this month, the shipbuilder broke this record with the delivery of a...

QatarEnergy LNG carrier wraps up trials in China

A 174,000-cbm liquefied natural gas (LNG) carrier built as part of the massive QatarEnergy shipbuilding program has completed its...