QatarEnergy, ExxonMobil moving forward with Golden Pass LNG work

Energy giants QatarEnergy and ExxonMobil released the latest construction update for their Golden Pass LNG export terminal on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities.

QatarEnergy, ExxonMobil moving forward with Golden Pass LNG work
Train 2 (Image: Golden Pass LNG)

Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas and flare wall modifications, continued piping and vessels insulation activities, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins in Trains 2 and 3, and progressed brownfield tie-ins and LNG tank tops modifications scope.

Golden Pass also progressed cable tray installations and cable pulling activities and continued pipe pneumatic / hydrostatic testing program.

As per the pipeline expansion project, Golden Pass continued civil activities and concrete foundation pours at milepost MP33 and MP69 compressor stations and also continued pipe fabrication and installation at these stations.

It also continued construction activities of the Sabine Spur, Natural Gas Pipeline (NGPL)
Interconnect improvements, and associated facilities.

QatarEnergy, ExxonMobil moving forward with Golden Pass LNG work
Flare area (Image: Golden Pass LNG)

H1 2025

Regarding the start of operations, the FERC said in an inspection report in November that the anticipated timing for the first Golden Pass train is the second half of 2024, with the second and the third train following after.

The anticipated in-service timing for the pipeline expansion project is expected sometime prior to the second half of 2024, it said.

ExxonMobil’s senior VP and CFO, Kathryn Mikellss, recently said that “train 1 mechanical completion is expected at the end of 2024 with first LNG in first half of 2025.”

The US currently exports LNG via Cheniere’s Sabine Pass and Corpus Christi plants, Sempra’s Cameron LNG terminal, Venture Global’s Calcasieu Pass facility, the Freeport LNG terminal, Berkshire Hathaway’s Cove Point terminal, and Kinder Morgan’s Elba Island facility.

Besides the Golden Pass LNG export plant, Venture Global expects to start commissioning its Plaquemines LNG facility this year.

Most Popular

Worley gets full notice to proceed on first phase of CP2 LNG project

Australian engineering firm Worley has received a full notice to proceed from US LNG exporter Venture Global LNG under its reimbursable EPC contract for the first phase of the CP2 LNG project in Louisiana.

Venture Global’s Plaquemines LNG to commission fourth tank

US LNG exporter Venture Global LNG has received approval from the US FERC to commission the fourth storage tank with LNG at its Plaquemines plant in Louisiana.

MOL’s LNG carrier fleet stands at 104 vessels

MOL's large fleet of liquefied natural gas (LNG) tankers had 104 vessels as of the end of June this year.

More News Like This

Knutsen takes delivery of QatarEnergy LNG carrier

Norwegian shipowner Knutsen has taken delivery of another 174,000-cbm liquefied natural gas (LNG) carrier built as part of the massive QatarEnergy shipbuilding program.

Golden Pass LNG gets new FERC approval as commissioning progresses

Golden Pass LNG, a joint venture owned by energy giants QatarEnergy and ExxonMobil, is moving forward with commissioning activities at its two-train LNG plant in Texas with a new approval from the US FERC.

QatarEnergy LNG carrier wraps up trials in China

A 174,000-cubic-meter liquefied natural gas (LNG) carrier, built as part of QatarEnergy's massive shipbuilding program, has completed its trials in China, according to Hudong-Zhonghua.

Santos inks LNG supply deal with QatarEnergy’s trading unit

Australian LNG player Santos has signed a mid-term LNG supply deal with QatarEnergy Trading, a unit of state-owned LNG giant QatarEnergy.