QatarEnergy, ExxonMobil moving forward with Golden Pass LNG work

Energy giants QatarEnergy and ExxonMobil released the latest construction update for their Golden Pass LNG export terminal on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities.

QatarEnergy, ExxonMobil moving forward with Golden Pass LNG work
Train 2 (Image: Golden Pass LNG)

Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas and flare wall modifications, continued piping and vessels insulation activities, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins in Trains 2 and 3, and progressed brownfield tie-ins and LNG tank tops modifications scope.

Golden Pass also progressed cable tray installations and cable pulling activities and continued pipe pneumatic / hydrostatic testing program.

As per the pipeline expansion project, Golden Pass continued civil activities and concrete foundation pours at milepost MP33 and MP69 compressor stations and also continued pipe fabrication and installation at these stations.

It also continued construction activities of the Sabine Spur, Natural Gas Pipeline (NGPL)
Interconnect improvements, and associated facilities.

QatarEnergy, ExxonMobil moving forward with Golden Pass LNG work
Flare area (Image: Golden Pass LNG)

H1 2025

Regarding the start of operations, the FERC said in an inspection report in November that the anticipated timing for the first Golden Pass train is the second half of 2024, with the second and the third train following after.

The anticipated in-service timing for the pipeline expansion project is expected sometime prior to the second half of 2024, it said.

ExxonMobil’s senior VP and CFO, Kathryn Mikellss, recently said that “train 1 mechanical completion is expected at the end of 2024 with first LNG in first half of 2025.”

The US currently exports LNG via Cheniere’s Sabine Pass and Corpus Christi plants, Sempra’s Cameron LNG terminal, Venture Global’s Calcasieu Pass facility, the Freeport LNG terminal, Berkshire Hathaway’s Cove Point terminal, and Kinder Morgan’s Elba Island facility.

Besides the Golden Pass LNG export plant, Venture Global expects to start commissioning its Plaquemines LNG facility this year.

Most Popular

Williams launches Transco pipeline expansions

US natural gas pipeline operator Williams has launched two fully contracted expansions of the existing Transco pipeline to meet growing domestic demand and LNG exports.

Update: Shell’s LNG Canada receives LNG cargo

Shell’s LNG Canada has received a cargo of liquefied natural gas as part of the commissioning and start-up phase.

DOE gives further boost to US LNG exports

The US Department of Energy (DOE) has removed a regulatory barrier that required liquefied natural gas (LNG) projects to start export within seven years of receiving regulatory approval.

More News Like This

Larsen & Toubro scores QatarEnergy LNG gig

A unit of India’s engineering and construction firm Larsen & Toubro has secured an offshore contract from LNG producer QatarEnergy LNG, a unit of QatarEnergy. This deal, worth more than $1.75 billion, is the largest single contract ever received by L&T.

QatarEnergy LNG carrier completes trials in China

A 174,000-cbm liquefied natural gas (LNG) carrier built as part of the massive QatarEnergy shipbuilding program has completed its trials in China, according to Hudong-Zhonghua.

Hanwha Ocean starts work on Nakilat’s LNG carrier

South Korean shipbuilder Hanwha Ocean has officially started building Nakilat's first of eight LNG carriers under the massive QatarEnergy shipbuilding program.

ARC Resources seals long-term LNG SPA with ExxonMobil

Canadian gas producer ARC Resources has signed a long-term sale and purchase agreement with a unit of US energy giant ExxonMobil for volumes from the Cedar LNG project in Canada.