BP’s Tortue FLNG project takes another step towards production in 2023

BP’s Greater Tortue Ahmeyim FLNG project located offshore Mauritania and Senegal continues to progress towards the start of production next year after the completion of 21 giant caissons that make up a breakwater for the development.

France’s Eiffage Genie Civil said in a statement last week it had completed the construction of 21 mega caissons at its Dakar site in Senegal.

The caissons, 16 of which have already been installed, would constitute the breakwater that would protect the project’s FLNG and LNG carriers offshore the coast of Saint-Louis, it said.

To build them, two plants operated by the Eiffage group produced more than 130,000 cubic meters of concrete.

Each caisson weighs 16,000 tonnes, is 55 m long, 28 meters wide, and 32 meters high, the firm said. The construction process required more than 1,700 workers.

According to Eiffage, the contractor would now work on constructing berthing facilities for the FLNG and LNG carriers.

BP’s Tortue FLNG project takes another step towards production in 2023
Gimi FLNG (Image: Golar LNG)

Gimi FLNG

Eiffage and Italy’s Saipem won the contract from BP for the Tortue development back in 2019.

The hub is located some ten kilometers from shore and includes the berthing facilities for the FLNG and the breakwater.

According to BP, the Tortue/Ahmeyim gas field, located offshore on the border between Mauritania and Senegal, has about 15 trillion cubic feet of gas.

The project’s FPSO will process the gas, removing heavier hydrocarbon components, prior to delivering it to the floating LNG provider which will be located at the hub.

Furthermore, Singapore’s Keppel shipyard is currently converting Golar’s Gimi FLNG for the project.

Golar said in November the FLNG was 75 percent technically complete. The yard should deliver the unit in 2023.

Once deployed offshore Mauritania and Senegal, it would provide about 2.5 million tonnes of LNG per annum on average.

Besides operator BP and Kosmos Energy, the project includes national oil companies Petrosen and SMHPM.

Most Popular

Shell wraps up acquisition of Pavilion Energy

UK-based LNG giant Shell has completed its previously announced acquisition of Singapore's Pavilion Energy.

India’s ONGC approves Mozambique LNG investment

India’s state-run ONGC has approved an investment by its unit, ONGC Videsh, into the TotalEnergies-led Mozambique LNG joint venture, which is developing a 12.8 mtpa liquefaction plant at the Afungi complex.

Australia’s Viva Energy seeks FSRU for Geelong project

Australia’s Viva Energy is looking to secure a floating storage and regasification Unit (FSRU) for its proposed LNG import terminal in Geelong, Australia.

More News Like This

BP takes FID on Ginger gas project in Trinidad and Tobago

UK-based energy giant BP has taken the final investment decision on the Ginger gas development offshore Trinidad and Tobago.

Argentina’s Enarsa gets offers for LNG cargo tender

Argentina's state-owned LNG importer Energia Argentina (Enarsa) has received seven offers for its first LNG cargo tender in 2025.

Shell CEO expects progress on Venture Global arbitration this year

Shell’s CEO Wael Sawan expects to have an update on an arbitration dispute with US LNG exporter Venture Global LNG later this year.

Golar seals $1.2 billion leasing deal for FLNG Gimi

Floating LNG player Golar LNG has entered into lease agreements with a consortium of Chinese leasing companies for the refinancing of the existing FLNG Gimi debt facility.