Construction progresses on Hong Kong’s first LNG import terminal

The developers behind Hong Kong’s first LNG import project, which includes the world’s largest FSRU, are moving forward with the construction works as they look to launch the facility later this year.

Hong Kong LNG Terminal, a joint venture consisting of HK Electric and Castle Peak Power (Capco), is developing the project.

Besides the 263,000-cbm MOL FSRU Challenger, to be renamed Bauhinia Spirit, the project features a double berth jetty.

The project forms part of Hong Kong’s initiative to reduce emissions. The city and special administrative region of China aims to replace about half of its power generation fuel with natural gas.

Regasified LNG coming from the FSRU will supply two power plants via subsea pipelines.

These include the Black Point power station located in the New Territories and Lamma power station located at Lamma Island.

Also, Shell will supply LNG as part of a long-term deal signed with the two utilities in 2019.

Commissioning scheduled in 2022

HK Electric said in its 2021 report on Tuesday that the FSRU-based project has passed “key
stages” of its development process.

These include vessel design upgrade, jetty construction, pipelaying, topside structure fabrication, and hydrostatic testing, according to the power utility.

“The terminal is scheduled for commissioning in 2022,” HK Electric said.

In November last year, the utility said the terminal could start operations in the middle of 2022.

One month later, Japan’s MOL and Dutch Vopak signed a deal to jointly own the giant FSRU which will serve the new LNG terminal in Hong Kong.

Under the deal, Vopak will buy 49.99 percent of the shares from MOL in the vessel owning company of the 2017-built, 345 meters long FSRU with a regasification capacity of 800 mmscfd.

MOL and Vopak will provide the FSRU as well as jetty operations and maintenance and port services to the project.

Prior to this deal, MOL and Vopak joined forces for the development of the project’s jetty and maintenance services.

The FSRU has still not arrived in Hong Kong. According to its AIS data provided by VesselsValue, the unit was on Tuesday located in the Suez Canal.

Most Popular

TotalEnergies to transfer Papua LNG operatorship to ExxonMobil

French energy giant TotalEnergies said on Monday that Papua LNG has achieved "major" contractual and commercial milestones, marking "decisive" steps towards a final investment decision. These include completing the EPC tendering process and transferring Papua LNG operatorship to US energy giant ExxonMobil, operator of the PNG LNG project.

Arctic LNG 2 seeks $1 billion from Hanwha Ocean over terminated LNG carrier orders

Novatek-led Arctic LNG 2 is seeking approximately $1 billion in damages from South Korean shipbuilder Hanwha Ocean over terminated shipbuilding contracts for Arc7 ice-class LNG tankers.

Gasunie, Vopak plan fifth Gate LNG jetty

Dutch partners Gasunie and Vopak plan to build a fifth liquefied natural gas (LNG) jetty at their Gate terminal in the port of Rotterdam.

More News Like This

Gasunie, Vopak plan fifth Gate LNG jetty

Dutch partners Gasunie and Vopak plan to build a fifth liquefied natural gas (LNG) jetty at their Gate terminal in the port of Rotterdam.

Japan’s MOL merges six ship management companies into one entity

Japanese shipping giant MOL, owner of a large LNG carrier fleet, has merged six of its ship management companies...

Cartagena FSRU in 200th STS LNG op

Colombia’s only FSRU-based LNG import facility in Cartagena has completed its 200th ship-to-ship transfer since 2016, according to SPEC LNG.

MOL expects to have 111 LNG carriers in its fleet by March 2027

Japan's shipping giant MOL still expects to have 111 liquefied natural gas (LNG) carriers in its fleet by March 2027.