Germany’s HEH: “great interest” in Stade LNG capacity booking

Germany’s Hanseatic Energy Hub, the developer of the Stade LNG import terminal near Hamburg, said market players have shown “great interest” to book capacity at the planned facility.

Last month, HEH invited international market participants to express their interest in booking long-term capacity in Stade from 2026 as it looks to accelerate the realization of the LNG import terminal with a capacity of 12 bcm per year.

HEH announced on Monday “very positive results” from its expression of interest process showing that the market has “great interest in capacity bookings at Stade.”

“What is needed now is a swift translation of the political signals in Germany into concrete measures: accelerated approval processes, flexible and swift procedures at BNetzA and, above all, equal treatment of all LNG projects,” the firm said.

HEH did not provide any additional information.

Germany plans several LNG import facilities

Germany currently has no large LNG import terminals but there are several facilities on the table including proposals from German LNG Terminal and Uniper, which received backing by the government.

Uniper and RWE are also finalizing talks to secure three floating storage and regasification units (FSRUs) for Germany as the country looks to ditch Russian gas supplies.

Last month, Germany’s HEH received approval from the local government for the planned Stade facility and signed a memorandum of understanding with German energy firm EnBW for capacity booking.

Current HEH partners include Germany’s Buss Group, Switzerland’s Partners Group, and Belgium’s Fluxys.

With its planned regasification capacity of 12 bcm per year, the LNG terminal in Stade would be able to cover about ten percent of Germany’s gas demand, according to HEH.

Located on the Elbe river within the Dow industrial park, the hub would initially handle LNG and low-carbon energy carriers such as bio-LNG and synthetic methane.

The concept also includes a truck loading facility and a jetty for bunkering vessels.

As global supply grows, it would later also be available for the import of “climate-neutral” energy sources such as ammonia, HEH previously said.

Most Popular

Knutsen’s LNG FSU ready for Honduras job

Knutsen’s 2004-built LNG carrier, Bilbao Knutsen, has been converted into a floating storage unit, and the vessel is ready to start serving an LNG-to-power project in Honduras.

Energy Transfer, EIG’s MidOcean to jointly develop Lake Charles LNG project

MidOcean Energy, the LNG unit of US-based energy investor EIG, has signed a heads of agreement with Energy Transfer to jointly develop the latter's Lake Charles LNG export facility in Louisiana.

CIMC SOE secures new LNG bunkering vessel order

China’s Nantong CIMC Sinopacific Offshore & Engineering has secured an order to build one liquefied natural gas (LNG) bunkering and supply vessel.

More News Like This

DET terminates Stade FSRU contract with HEH

State-owned German LNG terminal operator DET has terminated the contract related to the Stade FSRU-based facility with compatriot Hanseatic Energy Hub, the developer of the onshore LNG terminal in Stade.

Germany’s HEH appoints finance chief

Germany’s Hanseatic Energy Hub, the developer of the Stade LNG import terminal near Hamburg, has appointed Axel Zwanzig as...

DET moves Stade FSRU due to dredging work

State-owned German LNG terminal operator DET has temporarily relocated the 174,000-cbm FSRU Energos Force from the AVG jetty in...

HEH kicks off construction of Germany’s first onshore LNG import terminal

Germany’s Hanseatic Energy Hub has officially started building its Stade LNG import terminal near Hamburg worth about 1 billion...