Germany’s HEH to launch binding season for Stade LNG import terminal

Germany’s Hanseatic Energy Hub, the developer of the Stade LNG import terminal near Hamburg, is working to finalize the terms and conditions for a binding open season to enable its customers to secure capacity at the facility.

“As early as summer 2022, international market participants will be given an opportunity to submit binding requests for booking terminal capacity as part of a binding open season,” HEH said in a statement on Tuesday.

Last month, HEH said market players had shown “great interest” to book capacity at the facility as it looks to accelerate the realization of the LNG import terminal with a capacity of 13.3 bcm per year.

“The response to our expression-of-interest process in April has been extremely positive,” commercial director Danielle Stoves, said.

“Demand in the market is high and HEH is already in an advanced position with very detailed information available on the commercial and technical elements of the terminal,” Stoves said.

Germany to have several LNG import facilities

HEH said it started approval processes for the terminal and port, becoming Germany’s first LNG import project to do so.

Germany has no LNG terminals but it will build several plants as it looks to slash reliance on Russian gas. The country is also working on chartering four floating storage and regasification units (FSRUs).

HEH says the Stade capacity of 13.3 bcm per year corresponds to around 15 percent of Germany’s gas demand.

Besides LNG, the terminal developer also plans to import ammonia in the future.

Current HEH partners include Germany’s Buss Group, Switzerland’s Partners Group, and Belgium’s Fluxys.

In addition, US chemical firm Dow recently bought a minority stake in the LNG terminal developer.

This year, the JV received approval from the local government for the planned Stade facility. HEH also signed a memorandum of understanding with German energy firm EnBW for capacity booking.

HEH expects to take a final investment decision by 2023 and start importing LNG in 2026.

Most Popular

PetroVietnam Gas plans to deploy FSRU

PetroVietnam Gas, a unit of state-owned PetroVietnam, plans to deploy a floating storage and regasification unit in Vietnam next year, adding to its Thi Vai LNG import terminal.

Delfin secures DOE extension

Delfin Midstream, the US developer of a floating LNG export project offshore Louisiana. has secured a permit extension from the US Department of Energy, granting additional time to start exports from the FLNG project.

Japan’s Osaka Gas, partners to build LNG power plant

The CCGT unit will use regasified LNG as fuel, but it will also be able to consume e-methane in...

More News Like This

Germany’s HEH appoints finance chief

Germany’s Hanseatic Energy Hub, the developer of the Stade LNG import terminal near Hamburg, has appointed Axel Zwanzig as...

HEH kicks off construction of Germany’s first onshore LNG import terminal

Germany’s Hanseatic Energy Hub has officially started building its Stade LNG import terminal near Hamburg worth about 1 billion...

Germany’s HEH expands management team

Germany’s Hanseatic Energy Hub, developer of the Stade LNG import terminal near Hamburg, has appointed Alejandro Marjalizo as its...

Germany’s HEH takes FID on Stade LNG import terminal

Germany’s Hanseatic Energy Hub has taken a final investment decision to build its Stade LNG import terminal near Hamburg...