Cheniere says third Sabine Pass jetty almost 85 percent complete

US LNG exporting giant Cheniere and compatriot engineer Bechtel are moving forward with works on the third jetty at the six-train 30 mtpa Sabine Pass facility in Louisiana.

Cheniere is adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

It will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at the plant by 180 per year, Cheniere previously said.

Cheniere won approval from FERC to build the jetty in February 2020 and after that issued a notice to proceed to Bechtel.

According to the latest construction update filed with FERC, the project was 84.2 percent complete as of April this year, against the plan of 89.6 percent.

Cheniere said in the update that engineering was 100 percent complete, procurement 93.5 percent, subcontracts 96.6 percent, while construction was 64.2 percent complete.

Launch nearing

During the month of April, construction completed the setting of modules three and four, and finished erecting the stick-built piperack, according to Cheniere.

Following FERC authorization to install aboveground piping and equipment on April 8, 2022, hydrocarbon piping installation has started in the stickbuilt piperack, it said.

In addition, April activities also included the completion of the upper LNG transfer arms.

Cheniere did not reveal in the update when it expects to complete the jetty. In the original schedule, the firm had expected to launch the jetty in the first quarter of 2023.

However, Cheniere said in its May investor presentation that operations of the jetty could start by the end of this year.

High demand from Europe

Cheniere’s Sabine Pass and Corpus Christi plants shipped record number of LNG cargoes in the first quarter this year due to a surge in demand from Europe.

The two terminals exported in total 160 LNG cargoes, compared to 133 cargoes in the first quarter of 2020.

About 75 percent of these cargoes landed in Europe due to high prices and as European countries look to slash reliance on Russian gas.

Most Popular

Vopak moving forward with permitting process for Australian LNG import project

Dutch independent storage tank firm Vopak is moving forward with the permitting process for its planned FSRU-based LNG import facility in Australia’s Victoria state, according to CEO Dick Richelle.

Excelerate seals Bahamas LNG deal

US FSRU player Excelerate has signed an 11-year LNG supply agreement with AxDo, a joint venture between Axpo and Bahamas-based energy and maritime logistics company Domicisle LNG, supporting development of the Bahamas LNG hub.

PV Gas seeks new spot LNG shipment

Petrovietnam Gas, a unit of state-owned Petrovietnam, is seeking another spot LNG cargo for delivery to the Thi Vai LNG import terminal.

More News Like This

Cheniere in $1.2 billion senior notes offering

US LNG exporting giant Cheniere has priced its $1.2 billion offering of senior notes due in 2037.

Cheniere’s net income and revenue up in Q3

US LNG exporting giant Cheniere reported an 11.5 percent year-on-year increase in its third-quarter net income to $1.17 billion, while quarterly revenue rose 39 percent year-on-year to $6.17 billion.

Cheniere inks long-term LNG supply deals with QatarEnergy

US LNG exporter Cheniere has entered into long-term liquefied natural gas (LNG) sale and purchase agreements with state-owned LNG giant QatarEnergy to supply 4 million tonnes per annum (mtpa) of LNG through 2054.

Port of Corpus Christi says Q3 LNG volumes up 46 percent

The US Port of Corpus Christi in Texas reported a 46.2 percent year-on-year increase in liquefied natural gas (LNG) volumes in the third quarter.