Marathon secures more time for Kenai LNG import project

Marathon Petroleum’s unit Trans-Foreland Pipeline has won more time from US regulators to bring the closed Kenai LNG export plant in Alaska back online as an import facility.

The US Federal Energy Regulatory Commission (FERC) said in a letter dated August 16 that it “granted an extension of time until and including December 17, 2025 to complete and place into service the project.”

Trans-Foreland asked FERC in July for the three-year extension.

FERC authorized Trans-Foreland on December 17, 2020 to launch the LNG import facility in two years.

Trans-Foreland plans to construct, modify, and operate new facilities for the import of LNG at its existing Kenai LNG export terminal in Nikiski, Kenai Peninsula Borough, and deliver the fuel to its Kenai refinery adjacent to the plant.

The Kenai LNG cool down project would allow the plant to provide up to 7 million standard cubic feet per day of gas.

The firm said that “the onset and duration of the Covid-19 pandemic and the war in Ukraine have generated adverse economic and logistical conditions that slowed commercial progress and precluded Trans-Foreland from making its final investment decision (FID) for the project.”

TransForeland also said it had been actively seeking suitable suppliers and is monitoring markets for LNG.

Despite this delay, Trans-Foreland “is confident that the project continues to be commercially viable,” it said.

Most Popular

NextDecade releases Rio Grande LNG construction update

In July 2023, NextDecade took the final investment decision on the first three Rio Grande trains and completed $18.4 billion project financing. NextDecade awarded...

India boosts September LNG imports

The country imported about 2.90 billion cubic meters, or about 2.2 million metric tonnes, of LNG in September via...

First Gen’s Batangas FSRU gets new LNG cargo

The 162,000-cbm FSRU BW Batangas, owned by BW LNG and chartered by First Gen, received the cargo from the...

More News Like This

Venture Global’s Plaquemines LNG to commission fourth liquefaction block with nitrogen

According to a filing, the regulator approved the commissioning of the block on October 16. The FERC granted the commissioning...

US FERC to prepare supplemental EIS for NextDecade’s Rio Grande LNG

Last month, the US Court of Appeals for the D.C. Circuit issued an order vacating FERC’s remand authorization of...

Eagle LNG gets more time to build Jacksonville terminal

Back in September 2019, the FERC granted a five-year authorization to Eagle LNG Partners Jacksonville to site, construct, and...

Venture Global’s Plaquemines LNG gets OK to start cooldown activities

According to a FERC filling dated September 6, the regulator grated Venture Global Plaquemines LNG's request to "introduce hazardous...