Marathon secures more time for Kenai LNG import project

Marathon Petroleum’s unit Trans-Foreland Pipeline has won more time from US regulators to bring the closed Kenai LNG export plant in Alaska back online as an import facility.

The US Federal Energy Regulatory Commission (FERC) said in a letter dated August 16 that it “granted an extension of time until and including December 17, 2025 to complete and place into service the project.”

Trans-Foreland asked FERC in July for the three-year extension.

FERC authorized Trans-Foreland on December 17, 2020 to launch the LNG import facility in two years.

Trans-Foreland plans to construct, modify, and operate new facilities for the import of LNG at its existing Kenai LNG export terminal in Nikiski, Kenai Peninsula Borough, and deliver the fuel to its Kenai refinery adjacent to the plant.

The Kenai LNG cool down project would allow the plant to provide up to 7 million standard cubic feet per day of gas.

The firm said that “the onset and duration of the Covid-19 pandemic and the war in Ukraine have generated adverse economic and logistical conditions that slowed commercial progress and precluded Trans-Foreland from making its final investment decision (FID) for the project.”

TransForeland also said it had been actively seeking suitable suppliers and is monitoring markets for LNG.

Despite this delay, Trans-Foreland “is confident that the project continues to be commercially viable,” it said.

Most Popular

Woodside shuts down Pluto LNG plant

"On Monday, Woodside safely shut down the Pluto LNG facility due to a fault in the Pluto control system,"...

Argentina’s YPF joins PAE and Golar to develop FLNG project

Marin announced this move in a social media post on Sunday. The CEO congratulated PAE for entering, through Argentina's incentive...

New Fortress raises $1.2 billion from bond issue

The Wes Edens-led firm announced on Tuesday the completion of the first step of its $2.7 billion issuance of...

More News Like This

Cheniere’s Corpus Christi LNG expansion project to receive first gas

The US FERC said on Wednesday that it had granted Corpus Christi Liquefaction's request to introduce hydrocarbons to Train...

Venture Global moving forward with Plaquemines LNG commissioning

The regulator said in a filing dated November 6 that it grated Venture Global Plaquemines LNG's request to commission...

Golden Pass secures three-year extension to complete Texas LNG terminal

Under the original FERC order from 2016, Golden Pass LNG was required to complete and place into service the...

Cheniere’s Corpus Christi expansion project nears launch of LNG production

"Together with Bechtel, we continue to advance our Corpus Christi Stage 3 project ahead of schedule and anticipate achieving...