LNG Canada pipeline 83 percent done

TC Energy’s Coastal GasLink is moving forward with the construction work on the giant pipeline that will supply natural gas to the Shell-led LNG Canada export terminal in order to complete it by the end of this year.

Coastal GasLink said in a construction update on Thursday that the overall progress on the 670 kilometers long pipeline had reached 83 percent completion as of the end of December.

This compares to 81.2 percent completion at the end of November.

According to Coastal GasLink, there were 5,578 workers across the project route as of December 18, 2022.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023 but the costs will significantly rise.

In July last year, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said in November that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

LNG Canada 80 percent complete

As per the LNG Canada plant in Kitimat, the C$40 billion project is 80 percent complete, according to a recent statement by LNG Canada.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

The company is also planning a second stage of the project as well.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

- Advertisements -

Most Popular

QatarEnergy seals $6 billion deal with Chinese shipbuilder for 18 giant LNG carriers

State-owned LNG giant QatarEnergy has signed a major shipbuilding deal worth $6 billion with China State Shipbuilding Corp for...

NFE says ‘minor mechanical issue’ will not affect Altamira LNG launch

US LNG player New Fortress Energy said that "a minor technical issue" which took place last week on one...

TotalEnergies CEO: Mozambique LNG restart is not a matter of costs

French energy giant TotalEnergies had "good" discussions with Mozambique LNG contractors and they agreed not to inflate the costs...

More News Like This

Shell CEO: LNG Canada to start commissioning later this year

Shell’s LNG Canada terminal is more than 90 percent complete and the project is preparing to launch commissioning activities...

LNG Canada CEO: start-up activities will take more than a year to complete

Shell's LNG Canada project is now preparing to launch start-up activities next year and this program will take more...

HaiSea Marine takes delivery of its first LNG-powered tug

Turkey’s Sanmar has delivered the first of two LNG-powered tugs to Canada's HaiSea Marine, a joint venture majority owned...

Third LNG Canada electric tug delivered

HaiSea Marine’s third and final electric tugboat which will serve the Shell-led LNG Canada project is on its way...