TotalEnergies, ExxonMobil, Santos launch Papua LNG FEED

Operator TotalEnergies and its partners ExxonMobil and Santos have launched fully-integrated front-end engineering and design (FEED) for the Papua LNG project in Papua New Guinea.

TotalEnergies has a 40.1 percent operating stake in the LNG export project, ExxonMobil has 37.1 percent, and Santos owns a 22.8 percent interest.

In July last year, the Papua LNG joint venture launched the first phase of front-end engineering and design (FEED) studies for the LNG project’s upstream production facilities.

After that, Technip Energies, leader of a consortium with Australia’s Clough, won a contract to perform the front-end engineering design (FEED) for the project’s upstream production facilities.

The upstream production facilities cover the development of the Elk and Antelope onshore gas fields including the well pads and the central processing facility.

It also incorporates a carbon capture and sequestration (CCS) scheme to remove the fields’ native CO2 and reinject it into the reservoirs.

First production by end of 2027 or early 2028

Australia’s Santos announced the launch of fully-integrated FEED in a statement on Tuesday.

Papua LNG would have liquefaction capacity of up to six million tonnes of LNG per year with first production expected by the end of 2027 or early 2028, it said.

Following pre-FEED studies, the Papua LNG partners have selected a concept using four electric LNG trains (e-trains) with a combined capacity of four million tonnes per annum, Santos said.

The partners will build the trains within the existing PNG LNG terminal in Caution Bay, operated by ExxonMobil.

Also, selecting e-trains and re-injection of reservoir CO2 will reduce the carbon intensity of the project, the firm said.

Papua LNG has also secured access to up to two million tonnes of existing liquefaction capacity from PNG LNG.

Integrating the Papua LNG midstream development within PNG LNG maximizes the value of both projects and delivers increased capital efficiency by reducing upfront capital expenditure and maximizing integration synergies, Santos said.

PNG LNG will receive an access fee, pro-rata opex sharing and ongoing processing toll revenue that compensates PNG LNG for making the capacity available.

FID

The partners expect that the selected concept for Papua LNG would have a lower capital expenditure outcome than the previous concept.

Costs will be refined during the FEED phase and the project participants intend to explore project finance opportunities for a portion of the project cost, Santos said.

Santos said that the government of Papua New Guinea may exercise a back-in right for up to a 22.5 percent interest in the LNG project at the final investment decision.

Should PNG exercise its full back-in right, Santos’ interest in the project would reduce to 17.7 percent.

Santos also has a 42.5 percent interest in PNG LNG and announced a conditional agreement to sell a five per cent interest in PNG LNG to Kumul Petroleum.

ExxonMobil holds a 33.2 percent operating interest in PNG LNG.

The Papua LNG partners plan to take FID by the end of 2023 or early 2024, according to the firm.

TotalEnergies sells Papua LNG stake

According to a separate statement by TotalEnergies issued later on Tuesday, the firm signed a head of agreement with JX Nippon to sell a 2 percent interest (post Kumul back-in right) in Papua LNG.

JX Nippon is an affiliate of Eneos and already holds a 4.7 percent interest in PNG LNG.

TotalEnergies also said that the construction and operation of the Papua LNG electrical liquefaction trains will be delegated to ExxonMobil.

(Article updated with a statement by TotalEnergies.)

Most Popular

Venture Global seals new deals to support expansion of its power network

US LNG exporter Venture Global has entered into power and grid frame agreements with GE Vernova and Baker Hughes for up to 16 new, 720 MW power island units and associated power transformer equipment, supporting the continued expansion of its existing behind-the-meter, industrial power network that is not reliant on the grid.

Venture Global gets approval to place first Plaquemines LNG phase in service

Venture Global’s Plaquemines LNG has secured approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.

Hanwha Ocean, Posco plan to build LNG carrier with high-manganese steel tanks

South Korean shipbuilder Hanwha Ocean and steel producer Posco plan to build a liquefied natural gas (LNG) carrier equipped with high-manganese steel cargo tanks.

More News Like This

TotalEnergies expects Q3 LNG results to rise sharply

French energy giant TotalEnergies, one of the world’s largest LNG players, expects its integrated LNG results to rise sharply in the third quarter compared to the prior quarter, driven by higher prices.

TotalEnergies plans second Mozambique LNG phase

French energy giant TotalEnergies plans to expand its Mozambique LNG project, currently under construction in Cabo Delgado province, with a second phase, according to management.

TotalEnergies board backs CEO Pouyanne for another term

French energy giant and LNG player TotalEnergies said ​on Friday that ‌its board unanimously ​backed ​the renewal of ⁠chairman ​and ​CEO Patrick Pouyanne's mandate.

TotalEnergies, Amni take FID on Ima gas project to supply Nigeria LNG

French energy giant TotalEnergies and its partner Amni have taken the final investment decision for the development of the Ima gas project offshore Nigeria to supply Nigeria LNG’s Bonny Island export plant.