Shell’s LNG Canada gets last modules

The Shell-led LNG Canada project has taken delivery of its last large modules from China.

LNG Canada announced this milestone via social media on Thursday.

“This impressive piece of equipment will be used to operate one of four refrigerant compressors at our LNG export facility in Kitimat, in the traditional territory of the Haisla Nation,” it said.

“With construction now more than 80 percent overall, we’re getting ready to commission, start-up and operate,” LNG Canada said.

LNG Prime reported on March 8 that China Offshore Oil Engineering (COOEC), a unit of CNOOC, has delivered the last two modules it built for the giant Shell-led LNG Canada project.

To mark the completion of the project, which included the construction of in total 35 modules, COOEC hosted a ceremony on March 7 at its Qingdao yard.

COOEC loaded the last two modules on board Cosco Shipping’s semi-submersible vessel, Xiang An Kou.

This vessel was located in Kitimat, where the LNG plant is located, for about a month and departed on May 1, according to its AIS data provided by VesselsValue.

Besides these modules, COOEC-Fluor is also constructing modules for the project at its fabrication yard in Zhuhai.

Shell's LNG Canada gets last modules
Image: LNG Canada

These modules are part of the first phase of the LNG Canada project which includes building two liquefaction trains with a capacity of 14 mtpa.

Shell and its partners in the project expect to deliver the first cargo by the middle of this decade, and they are also evaluating the second phase of the project.

Other partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Japan’s K Line on track with LNG fleet growth plans

According to K Line's latest financial report, the firm had 46 LNG carriers in its fleet as of the...

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

Tellurian’s unit seeks more time to build two gas pipelines

Last month, Australia's Woodside acquired all issued and outstanding Tellurian common stock for about $900 million cash, or $1.00 per...

More News Like This

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

Shell boosts European LNG bunkering business with new barge

Energy giant Shell has boosted its LNG bunkering business in Europe by adding a new inland LNG bunkering barge. Türkiye’s...

Shell wins appeal against Dutch court order on carbon emissions

The Hague District Court ordered Shell in a ruling in May 2021 to reduce its CO2 emissions by 45 percent by...

Woodfibre LNG appoints new CEO

According to a Woodfibre LNG statement, Schauerte brings more than 20 years of experience in the Canadian and global...