Construction progress continues on Golden Pass LNG export terminal

QatarEnergy and ExxonMobil are moving forward with the construction of their Golden Pass LNG export terminal on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mpta and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the three the trains next to the existing LNG import terminal.

“Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water
protection, levee construction, stockpiling of material, and piling,” Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC.

QatarEnergy and ExxonMobil update on Golden Pass LNG work
Ground flares (Image: Golden Pass)

First LNG train expected to go online in 2024

Golden Pass and its contractors progressed installation of piping and steel in process areas, continued walls and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass continued fin fan installation in the Train 1 main piperack and progressed setting various vessels on respective foundations and continued preparatory activities for Brownfield tie-ins and LNG tanks top modifications scope.

The firm said that structural steel installation continued around the brownfield boil-off gas compressors, while it is also preparing equipment insulation in condensate area.

QatarEnergy and ExxonMobil update on Golden Pass LNG work
Brownfield 6200 piperack (Image: Golden Pass)

As per the pipeline expansion project, Golden Pass continued civil and construction activities supporting milepost (MP)01 compressor station, Sabine Spur, Natural Gas Pipeline (NGPL) Interconnect improvements, and associated facilities.

It also continued mobilization and civil activities at the MP33 and MP69 compressor station areas.

FERC said in an inspection report last month that the anticipated in-service timing for the first train is the first quarter of 2024, the third quarter of 2024 for the second train, and the first quarter of 2025 for the third train.

- Advertisements -

Most Popular

Commissioning of India’s Chhara LNG terminal delayed

India’s Hindustan Petroleum, a unit of state-owned ONGC, has reportedly delayed the commissioning of its Chhara LNG import terminal...

MOL’s LNG carrier fleet to grow to 104 vessels by March 2025

Japan's shipping giant MOL expects its huge fleet of liquefied natural gas (LNG) carriers to increase to 104 vessels...

Venture Global: Plaquemines LNG to start production in mid-2024

US LNG exporter Venture Global LNG expects to start LNG production at its Plaquemines LNG export plant in Louisiana...

More News Like This

QatarEnergy seals $6 billion deal with Chinese shipbuilder for 18 giant LNG carriers

State-owned LNG giant QatarEnergy has signed a major shipbuilding deal worth $6 billion with China State Shipbuilding Corp for...

Papua New Guinea’s Kumul sells its first spot LNG cargo

Papua New Guinea’s national oil and gas company Kumul Petroleum said it had sold its first spot liquefied natural...

GTT secures LNG tank gig for eight vessels

French LNG containment giant GTT has secured a tank design order for eight 174,000-cbm LNG carriers. GTT said a statement...

PetroVietnam Gas: Thi Vai terminal receives second LNG cargo

PetroVietnam Gas, a unit of state-owned PetroVietnam, has received the second liquefied natural gas cargo at its Thi Vai...