Golden Pass LNG construction moving forward

QatarEnergy and ExxonMobil continue to make progress in building their giant Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mpta and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains next to the existing LNG import terminal.

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water protection, levee construction, stockpiling of material, and piling.

Golden Pass LNG export terminal
Second LNG train (Image: Golden Pass)

First LNG supplies in 2024

Golden Pass and its contractors progressed installation of piping and steel in process areas, continued walls and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins.

The firm also continued LNG tank tops modifications and progressed cable tray installations and cable pulling activities.

As per the pipeline expansion project, Golden Pass continued civil and construction activities supporting milepost (MP)01 Compressor Station, Sabine Spur, Natural Gas Pipeline (NGPL) Interconnect improvements, and associated facilities.

FERC said in an inspection report last month that the anticipated in-service timing for the first train is the second half of 2024, with the second and the third train following after.

The regulator said in inspections reports earlier this year that the anticipated in-service timing for the first train was the first quarter of 2024.

QatarEnergy’s CEO Saad Sherida Al-Kaabi said this week in Vancouver during LNG 2023 that 40 percent of all the new LNG supplies that will come to the market by 2029, will be from QatarEnergy’s projects.

He said that QatarEnergy is increasing production to 126 million tons per annum in Qatar and “we have another 16-18 MTPA out of the US coming online next year.”

Most Popular

Williams launches Transco pipeline expansions

US natural gas pipeline operator Williams has launched two fully contracted expansions of the existing Transco pipeline to meet growing domestic demand and LNG exports.

Update: Shell’s LNG Canada receives LNG cargo

Shell’s LNG Canada has received a cargo of liquefied natural gas as part of the commissioning and start-up phase.

DOE gives further boost to US LNG exports

The US Department of Energy (DOE) has removed a regulatory barrier that required liquefied natural gas (LNG) projects to start export within seven years of receiving regulatory approval.

More News Like This

Larsen & Toubro scores QatarEnergy LNG gig

A unit of India’s engineering and construction firm Larsen & Toubro has secured an offshore contract from LNG producer QatarEnergy LNG, a unit of QatarEnergy. This deal, worth more than $1.75 billion, is the largest single contract ever received by L&T.

QatarEnergy LNG carrier completes trials in China

A 174,000-cbm liquefied natural gas (LNG) carrier built as part of the massive QatarEnergy shipbuilding program has completed its trials in China, according to Hudong-Zhonghua.

Hanwha Ocean starts work on Nakilat’s LNG carrier

South Korean shipbuilder Hanwha Ocean has officially started building Nakilat's first of eight LNG carriers under the massive QatarEnergy shipbuilding program.

ARC Resources seals long-term LNG SPA with ExxonMobil

Canadian gas producer ARC Resources has signed a long-term sale and purchase agreement with a unit of US energy giant ExxonMobil for volumes from the Cedar LNG project in Canada.