LNG Canada wraps up tank test

Shell’s LNG Canada and its contractors have completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

The test included pumping 170,000 cbm of water into the large tank with a capacity of 225,000 cbm.

“This critical procedure, also known as hydrostatic testing, ensures LNG tank safety and reliability, and regulatory compliance,” LNG Canada said.

LNG Canada said this achievement is a “major step forward” as it works to ship its first cargoes by mid-decade.

Main contractor JGC Fluor recently also completed the module fabrication program for LNG Canada.

Overall, a total of 215 modules of varying sizes have been received and are being set at the project site.

This includes 35 large modules built by China Offshore Oil Engineering (COOEC), a unit of CNOOC, at its Qingdao yard.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

Atlantic and Pacific LNG rates continue to decrease

Atlantic and Pacific spot liquefied natural gas (LNG) shipping rates dropped for the second week in a row, according to Spark Commodities.

Cheniere’s Sabine Pass LNG expansion project gets OK from FERC

The US Federal Energy Regulatory Commission (FERC) has approved Cheniere’s planned Sabine Pass Stage 5 LNG expansion project in Louisiana.

Hanwha Ocean and Kanata advance Canada FLNG plans

South Korea’s Hanwha Ocean has entered into a heads of agreement with Canada’s Kanata Clean Power & Climate Technologies to advance the proposed $15.7 billion floating liquefied natural gas export project in Prince Rupert, British Columbia.

More News Like This

Vinci scores LNG Canada tank gig

A unit of French construction company Vinci has secured a contract from a joint venture of US engineer Fluor and Japan’s JGC to build one 225,000-cbm LNG storage tank for the Shell-led LNG Canada Phase 2 project in Kitimat, British Columbia.

Shell kicks off production at Malaysian gas field

UK-based LNG giant Shell has started natural gas production from the Rosmari and Marjoram gas fields offshore Malaysia, which will feed the Petronas-operated Bintulu LNG export plant in Sarawak.

Peru LNG sent five shipments in October

Peru LNG’s liquefaction plant at Pampa Melchorita shipped five liquefied natural gas cargoes in October, one cargo more compared to the previous month, according to shipment data by state-owned Perupetro.

Yokogawa bags LNG Canada Phase 2 gig

A unit of Japanese engineering firm Yokogawa has secured a contract from a joint venture of US engineer Fluor and Japan’s JGC to serve as the main automation contractor for the Shell-led LNG Canada Phase 2 project in Kitimat, British Columbia.