Chevron says third Gorgon LNG train returns to full production

The third liquefaction train at Chevron’s giant Gorgon LNG plant in Western Australia has returned to full production, Chevron told LNG Prime on Wednesday.

A Chevron spokesperson said that Gorgon Train 3 had returned to full production “over the past few days.”

The spokesperson did not provide any additional information.

Earlier this month, Chevron said that an electrical incident occurred on October 31 in a substation which provides power supply, resulting in the plant’s third train to produce at 80 percent capacity.

Chevron said domestic gas and the remaining two LNG production trains at the Gorgon plant were unaffected.

The Gorgon LNG plant on Barrow Island has three trains and a production capacity of some 15.6 mtpa.

Chevron and its workers at the Gorgon and Wheatstone LNG terminals recently agreed on new labor agreements following lengthy negotiations between Chevron and unions representing the workers.

In September, Chevron also resumed full production at its 8.9 mtpa Wheatstone LNG terminal near Onslow after a fault reduced about 25 percent of the plant’s production.

Most Popular

NextDecade’s Rio Grande LNG secures final FERC approval

The US Federal Energy Regulatory Commission (FERC) has issued its final order for NextDecade's Rio Grande LNG facility and the accompanying pipeline in Texas.

Poland’s Gaz-System revives plan for second Gdansk FSRU

Poland’s state-owned LNG terminal operator Gaz-System has revived its plan to add a second FSRU as part of the LNG import project in Gdansk Bay with a new non-binding call for interest.

Capital sells another LNG carrier for scrap

Greece's Capital Gas has sold another steam liquefied natural gas (LNG) carrier for scrap, according to brokers.

More News Like This

Chevron, China’s ENN seal second LNG SPA

US energy giant Chevron has signed a second LNG sales and purchase agreement with Chinese independent gas distributor ENN.

Energy Transfer, Chevron expand Lake Charles LNG deal

Energy Transfer, the developer of the proposed Lake Charles LNG export facility in Louisiana, has signed a new deal with energy giant Chevron for additional LNG volumes.

Chevron: Wheatstone LNG ships 1000th cargo

The Chevron-operated Wheatstone LNG plant in Western Australia has shipped its 1000th cargo of liquefied natural gas since 2017.

Chevron: production at first Wheatstone LNG train reduced due to maintenance

Production at the first liquefaction train of Chevron's Wheatstone LNG plant near Onslow has been reduced due to maintenance, a Chevron Australia spokesperson told LNG Prime on Tuesday.