Construction progress continues on Golden Pass LNG export plant

Energy giants QatarEnergy and ExxonMobil released the latest construction update for their Golden Pass liquefied natural gas (LNG) export terminal on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

Construction progress continues on Golden Pass LNG export plant
LNG trains (Image: Golden Pass LNG)

First train expected to start ops in 2024

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water protection, levee construction, stockpiling of material, and piling.

Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas, continued piping and vessels insulation activities and helical piles and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins in Trains 2 and 3, and progressed brownfield tie-ins and LNG tank tops modifications scope.

Golden Pass also progressed cable tray installations and cable pulling activities and continued pipe pneumatic / hydrostatic testing program.

Construction progress continues on Golden Pass LNG export plant
Ground flares (Image: Golden Pass LNG)

As per the pipeline expansion project, Golden Pass continued civil activities and concrete foundation pours at milepost MP33 and MP69 compressor stations and also continued pipe fabrication and installation at these stations.

It also continued construction activities of the Sabine Spur, Natural Gas Pipeline (NGPL)
Interconnect improvements, and associated facilities.

Regarding the start of operations, the FERC said in an inspection report in October that the anticipated in-service timing for the first Golden Pass train is the second half of 2024, with the second and the third train following after.

The anticipated in-service timing for the pipeline expansion project is expected sometime prior to the second half of 2024, it said.

The US currently exports LNG via Cheniere’s Sabine Pass and Corpus Christi plants, Sempra’s Cameron LNG terminal, Venture Global’s Calcasieu Pass facility, the Freeport LNG terminal, Berkshire Hathaway’s Cove Point terminal, and Kinder Morgan’s Elba Island facility.

Besides the Golden Pass LNG export plant, Venture Global expects to launch its Plaquemines LNG facility next year as well.

Most Popular

TotalEnergies board backs CEO Pouyanne for another term

French energy giant and LNG player TotalEnergies said ​on Friday that ‌its board unanimously ​backed ​the renewal of ⁠chairman ​and ​CEO Patrick Pouyanne's mandate.

NYK’s LNG carrier named in South Korea

South Korea’s Hyundai Samho hosted a naming ceremony for a new liquefied natural gas (LNG) carrier owned by Japan's NYK and chartered by Mitsubishi’s unit Diamond Global Energy.

China Harbour bags Nigeria LNG contract

China Harbour Engineering Company (CHEC) said it has secured a contract related to the construction of Nigeria LNG's seventh...

More News Like This

ExxonMobil’s Rovuma LNG seeks contractor for land transportation services

US energy giant ExxonMobil and its partners in the planned Rovuma LNG project in Mozambique have invited companies to submit expressions of interest to provide land transportation services.

ExxonMobil’s PNG LNG hits production milestone

The ExxonMobil-operated PNG LNG project in Papua New Guinea has reached a new milestone, producing more than 100 million tons of liquefied natural gas (LNG) since operations began in 2014.

QatarEnergy CEO says damaged Ras Laffan LNG trains to take three years to repair

State-owned LNG giant QatarEnergy expects the damage to two liquefaction trains at its giant Ras Laffan complex to take three years to repair, according to Qatar’s energy minister and CEO of QatarEnergy, Saad Sherida Al-Kaabi.

Wood bags PNG LNG gig

UK-based consulting and engineering firm Wood has secured a contract for the ExxonMobil-operated PNG LNG project in Papua New Guinea.