BP’s Tortue FLNG project takes another step towards production in 2023

BP’s Greater Tortue Ahmeyim FLNG project located offshore Mauritania and Senegal continues to progress towards the start of production next year after the completion of 21 giant caissons that make up a breakwater for the development.

France’s Eiffage Genie Civil said in a statement last week it had completed the construction of 21 mega caissons at its Dakar site in Senegal.

The caissons, 16 of which have already been installed, would constitute the breakwater that would protect the project’s FLNG and LNG carriers offshore the coast of Saint-Louis, it said.

To build them, two plants operated by the Eiffage group produced more than 130,000 cubic meters of concrete.

Each caisson weighs 16,000 tonnes, is 55 m long, 28 meters wide, and 32 meters high, the firm said. The construction process required more than 1,700 workers.

According to Eiffage, the contractor would now work on constructing berthing facilities for the FLNG and LNG carriers.

BP’s Tortue FLNG project takes another step towards production in 2023
Gimi FLNG (Image: Golar LNG)

Gimi FLNG

Eiffage and Italy’s Saipem won the contract from BP for the Tortue development back in 2019.

The hub is located some ten kilometers from shore and includes the berthing facilities for the FLNG and the breakwater.

According to BP, the Tortue/Ahmeyim gas field, located offshore on the border between Mauritania and Senegal, has about 15 trillion cubic feet of gas.

The project’s FPSO will process the gas, removing heavier hydrocarbon components, prior to delivering it to the floating LNG provider which will be located at the hub.

Furthermore, Singapore’s Keppel shipyard is currently converting Golar’s Gimi FLNG for the project.

Golar said in November the FLNG was 75 percent technically complete. The yard should deliver the unit in 2023.

Once deployed offshore Mauritania and Senegal, it would provide about 2.5 million tonnes of LNG per annum on average.

Besides operator BP and Kosmos Energy, the project includes national oil companies Petrosen and SMHPM.

Most Popular

Japan’s MOL merges six ship management companies into one entity

Japanese shipping giant MOL, owner of a large LNG carrier fleet, has merged six of its ship management companies...

Germany’s BASF gets first LNG cargo under Cheniere contract

German chemicals giant BASF has received its first liquefied natural gas (LNG) cargo under a long-term contract with US LNG exporter Cheniere.

Top 5 news of the week August 24-30

LNG Prime brings you the five most popular news stories on our platform during the week of August 24-30, 2026.

More News Like This

BP, XRG secure license for Venezuela offshore gas field

UK-based energy giant BP, Adnoc's international investment unit XRG, and a unit of Qatar's UCC have secured a license to explore and develop the second phase of Venezuela's offshore Loran gas field.

McDermott JV lands Rovuma LNG gig

Houston-based McDermott, through a consortium with Italy’s Saipem, South Korea's Daewoo Engineering & Construction, and China Petroleum Engineering and Construction Corporation, has been awarded a letter of intent including limited engineering and procurement services for the ExxonMobil-led Rovuma LNG project in Mozambique.

BP to take full control of Trinidad gas project

UK-based energy giant BP has agreed to acquire Woodside’s 70 percent interest in the Calypso gas project in Trinidad and Tobago, increasing its stake to 100 percent and assuming operatorship.

BP to supply another spot LNG cargo to Pakistan

A unit of UK-based energy giant BP has submitted the lowest bid in a tender to supply Pakistan with one spot LNG shipment this week.