Kosmos: BP’s Tortue FLNG project 75 percent complete

BP’s Greater Tortue Ahmeyim FLNG project located offshore Mauritania and Senegal has reached a 75 percent completion mark at the end of the first quarter, project partner Kosmos Energy said on Monday.

Texas-based Kosmos said in its quarterly results report that the first phase of the Greater Tortue Ahmeyim LNG project has reached several milestones during the January-March period.

The project includes the conversion of Golar LNG’s Gimi to a floating LNG producer at Singapore’s Keppel shipyard and the construction of the FPSO by Technip Energies at COSCO Shipping’s Qidong yard in China.

Kosmos said in the update that Keppel had commenced pipe rack outfitting and equipment installation and testing.

The 2.5 mtpa Gimi FLNG should start serving BP’s Greater Tortue Ahmeyim project under a 20-year deal next year.

Golar said last month that the conversion was about 82 percent technically complete as of April 14.

As per the FPSO, Kosmos said work on the FPSO in the shipyard continues with mechanical completion activities and inspection tests.

Besides the works at the two yards, construction work continues to progress offshore Mauritania and Senegal.

Earlier this year, France’s Eiffage Genie Civil said it had completed the construction of 21 mega caissons at its Dakar site in Senegal.

The caissons will constitute the breakwater that will protect the project’s FLNG and LNG carriers offshore the coast of Saint-Louis.

Kosmos said that the yard has shipped the 21st and final caisson shipped offshore in early March 2022. There are three caissons left to be installed at the hub terminal.

In addition, Kosmos expects the subsea construction campaign to start in May, while drilling has commenced with top holes completed on two of the four wells required for first gas.

Most Popular

Venture Global gets FERC OK to boost Plaquemines LNG capacity

US LNG exporter Venture Global LNG has received approval from the US FERC to boost the capacity of its Plaquemines LNG terminal in Louisiana to 27.2 mtpa.

First Rio Grande LNG tank taking shape

US LNG developer NextDecade continues to make progress on the first phase of its Rio Grande LNG export plant in Texas, including the first 180,000-cbm storage tank.

Cheniere produces first LNG cargo at Corpus Christi expansion project

US LNG exporting giant Cheniere has produced the first cargo at the Corpus Christi Stage 3 expansion project in Texas.

More News Like This

Venture Global says to launch Calcasieu Pass LNG commercial ops in April

US LNG exporter Venture Global LNG expects to launch commercial operations at its Calcasieu Pass LNG terminal in Louisiana in April, some 68 months from its final investment decision and 38 months after production start.

BP chief expects ruling on Venture Global dispute later this year

BP's CEO Murray Auchincloss expects a ruling on an arbitration dispute with US LNG exporter Venture Global LNG to be delivered in the second half of this year.

BP, partners achieve first LNG at Tortue project

UK-based energy giant BP and its partners have started producing liquefied natural gas (LNG) at the Greater Tortue Ahmeyim FLNG project, located offshore Mauritania and Senegal.

BP delivers US LNG cargo to Bulgargaz via Alexandroupolis FSRU

The 2021-built 174,000-cbm, BW Lesmes, delivered the shipment to the 153,500-cbm FSRU, Alexandroupolis, on January 19, a spokeswoman for...