Cheniere: Corpus Christi LNG expansion project 43 percent complete

US LNG exporting giant Cheniere and compatriot construction and engineering firm Bechtel are moving forward with the construction work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

In June last year, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the August construction report filed with the US FERC that overall project completion for the Stage 3 project is 42.8 percent.

Stage 3 engineering and procurement are 70.9 percent and 62.3 percent complete, respectively, while subcontract and direct hire construction work are 54 percent and 6.5 percent complete, respectively, it said.

Cheniere: Corpus Christi LNG expansion project 43 percent complete
Cryo piperack — first spools in rack for Train 1 (Image: Cheniere)

First cold boxes arrived

During the month of August, CCL’s contractor continued piling activities, road improvements, drainage work and mobilization of temporary facilities, equipment, and personnel continued during the reporting period, it said.

CCL said that Bechtel has started installation of aboveground piping and it has established a new workstation for double jointing pipe.

In addition, the first cold boxes arrived at the site.

Last year, US equipment manufacturer Chart Industries received full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

CCL said that Bechtel has completed piling work for Trains 1-3 with the same work ongoing for the remaining four trains and OSBL areas.

Steel installation is progressing on schedule in Train 1 and preparations are being made to start steel installation in Train 2.

Additionally, piling installation begun for the 138 kV overhead line transition yard and work on the overhead line poles has started, it said.

Cheniere: Corpus Christi LNG expansion project 43 percent complete
Preparation for piperack foundation pedestals work and feed gas line (Image: Cheniere)

Ahead of schedule

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August that the company is expecting to complete the expansion phase ahead of schedule.

Fusco told analysts during Cheniere’s second-quarter earnings call that Bechtel “continues to progress Corpus Christi Stage 3 well ahead of schedule, increasing my optimism for that project being completed ahead of the guaranteed date.”

“Certain construction activities on Stage 3 are taking place ahead of plan, and I remain optimistic on schedule outperformance and potentially having more LNG volumes in 2025, and possibly the entire seven-train project complete by the end of 2026,” the CEO said.

Most Popular

Venture Global eyes FID on second CP2 phase in 2026

US LNG exporter Venture Global LNG expects to make a final investment decision on the second phase of its CP2 LNG project in Louisiana in 2026, according to CEO Mike Sabel.

Excelerate eyes LNG bunkering infrastructure

US FSRU player Excelerate Energy is interested in LNG bunkering infrastructure opportunities as the global fleet of LNG-fueled vessels continues to expand, according to CEO Steven Kobos.

HD Hyundai Heavy to build LNG carrier duo

South Korean shipbuilder HD Hyundai Heavy Industries has won a contract worth approximately $494 million to build two liquefied natural gas (LNG) carriers.

More News Like This

Cheniere in $1.2 billion senior notes offering

US LNG exporting giant Cheniere has priced its $1.2 billion offering of senior notes due in 2037.

Cheniere’s net income and revenue up in Q3

US LNG exporting giant Cheniere reported an 11.5 percent year-on-year increase in its third-quarter net income to $1.17 billion, while quarterly revenue rose 39 percent year-on-year to $6.17 billion.

Cheniere inks long-term LNG supply deals with QatarEnergy

US LNG exporter Cheniere has entered into long-term liquefied natural gas (LNG) sale and purchase agreements with state-owned LNG giant QatarEnergy to supply 4 million tonnes per annum (mtpa) of LNG through 2054.

Port of Corpus Christi says Q3 LNG volumes up 46 percent

The US Port of Corpus Christi in Texas reported a 46.2 percent year-on-year increase in liquefied natural gas (LNG) volumes in the third quarter.