Cheniere: third Sabine Pass jetty more than 90 percent complete

US LNG exporting giant Cheniere and compatriot engineer Bechtel have completed more than 90 percent of the third jetty project at the six-train 30 mtpa Sabine Pass facility in Louisiana.

Cheniere is adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

It will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at the plant by 180 per year.

Cheniere won approval from FERC to build the jetty in February 2020 and after that issued a notice to proceed to Bechtel.

90.3 percent complete

According to the latest construction update filed with FERC, the project was 90.3 percent complete as of May this year, against the plan of 91.6 percent. This compares to 84.2 percent in April.

Cheniere said in the update that engineering was 100 percent complete, procurement 100 percent, subcontracts 97.7 percent, while construction was 73.1 percent complete.

During the month of May, construction completed preparations for energization of the jetty
substation and successfully energized at the end of May, according to Cheniere.

The construction of the LNG trench and slope protection continued, while pipe insultation of the hydrocarbon lines started as well, the LNG producer said.

June works

During June, Cheniere plans to complete slope protection and concrete placements for LNG
trench, as well as to start system turnover from construction to CSU and to begin loop checks at the loading platform.

Cheniere did not reveal in the update when it expects to complete the jetty. In the original schedule, the firm had expected to launch the jetty in the first quarter of 2023.

However, Cheniere said in its May investor presentation that operations of the jetty could start by the end of this year.

Most Popular

Energy Transfer seals Lake Charles LNG supply deals

Texas-based Energy Transfer has signed new supply deals for its planned Lake Charles LNG export facility in Louisiana as it works to take a final investment decision by the end of this year, according to its management.

Samsung Heavy develops new FLNG concept

South Korean shipbuilding giant Samsung Heavy Industries has received approvals from three classification societies for its new multi-purpose FLNG concept.

ExxonMobil CEO expects Golden Pass LNG launch by end of this year

ExxonMobil CEO Darren Woods expects the QatarEnergy-led Golden Pass LNG export project in Texas to produce first LNG volumes by the end of this year. Separately, Golden Pass LNG is also seeking approval from the US FERC to increase peak workforce up to 10,300.

More News Like This

Cheniere reports higher Q1 revenue

US LNG exporting giant Cheniere reported a rise in its quarterly revenue due to higher prices, while its net profit decreased compared to the same period last year.

Cheniere to introduce fuel gas to second Corpus Christi LNG expansion train

US LNG exporter Cheniere is nearing the introduction of fuel gas to the second train of the Corpus Christi Stage 3 expansion project in Texas as part of the commissioning phase.

Three dead in accident at Port Arthur LNG site

Sempra Infrastructure and Bechtel confirmed that an incident took place on Tuesday at the Port Arthur LNG construction site in Texas, resulting in three fatalities and two injuries.

Cheniere’s Corpus Christi expansion project 82.5 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 82.5 percent complete.