Cheniere says third Sabine Pass jetty almost 85 percent complete

US LNG exporting giant Cheniere and compatriot engineer Bechtel are moving forward with works on the third jetty at the six-train 30 mtpa Sabine Pass facility in Louisiana.

Cheniere is adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

It will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at the plant by 180 per year, Cheniere previously said.

Cheniere won approval from FERC to build the jetty in February 2020 and after that issued a notice to proceed to Bechtel.

According to the latest construction update filed with FERC, the project was 84.2 percent complete as of April this year, against the plan of 89.6 percent.

Cheniere said in the update that engineering was 100 percent complete, procurement 93.5 percent, subcontracts 96.6 percent, while construction was 64.2 percent complete.

Launch nearing

During the month of April, construction completed the setting of modules three and four, and finished erecting the stick-built piperack, according to Cheniere.

Following FERC authorization to install aboveground piping and equipment on April 8, 2022, hydrocarbon piping installation has started in the stickbuilt piperack, it said.

In addition, April activities also included the completion of the upper LNG transfer arms.

Cheniere did not reveal in the update when it expects to complete the jetty. In the original schedule, the firm had expected to launch the jetty in the first quarter of 2023.

However, Cheniere said in its May investor presentation that operations of the jetty could start by the end of this year.

High demand from Europe

Cheniere’s Sabine Pass and Corpus Christi plants shipped record number of LNG cargoes in the first quarter this year due to a surge in demand from Europe.

The two terminals exported in total 160 LNG cargoes, compared to 133 cargoes in the first quarter of 2020.

About 75 percent of these cargoes landed in Europe due to high prices and as European countries look to slash reliance on Russian gas.

Most Popular

QatarEnergy CEO says damaged Ras Laffan LNG trains to take three years to repair

State-owned LNG giant QatarEnergy expects the damage to two liquefaction trains at its giant Ras Laffan complex to take three years to repair, according to Qatar’s energy minister and CEO of QatarEnergy, Saad Sherida Al-Kaabi.

Glencore pens Chinese LNG supply deal

Switzerland-based energy trader Glencore has signed a long-term deal to supply liquefied natural gas (LNG) to a unit of China Suntien Green Energy.

Equinor seals long-term LNG SPA with Thailand’s PTT

Norwegian energy firm Equinor has signed a long-term LNG sales and purchase agreement with a unit of Thailand’s PTT.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project more than 50 percent complete

Cheniere's Corpus Christi Midscale Trains 8 and 9 project in Texas is more than 50 percent complete, according to the latest construction update.

Equinor takes first LNG cargo from Cheniere

Norwegian energy firm Equinor has taken delivery of its first liquefied natural gas (LNG) cargo under long-term supply agreements with US LNG exporting giant Cheniere.

Cheniere completes CCL Stage 3 project

US LNG exporter Cheniere has completed the Corpus Christi Liquefaction Stage 3 expansion project in Texas. In addition, Cheniere has also exported its 5,000th LNG cargo since 2016.

Germany’s BASF gets first LNG cargo under Cheniere contract

German chemicals giant BASF has received its first liquefied natural gas (LNG) cargo under a long-term contract with US LNG exporter Cheniere.