Cheniere says third Sabine Pass jetty almost 85 percent complete

US LNG exporting giant Cheniere and compatriot engineer Bechtel are moving forward with works on the third jetty at the six-train 30 mtpa Sabine Pass facility in Louisiana.

Cheniere is adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

It will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at the plant by 180 per year, Cheniere previously said.

Cheniere won approval from FERC to build the jetty in February 2020 and after that issued a notice to proceed to Bechtel.

According to the latest construction update filed with FERC, the project was 84.2 percent complete as of April this year, against the plan of 89.6 percent.

Cheniere said in the update that engineering was 100 percent complete, procurement 93.5 percent, subcontracts 96.6 percent, while construction was 64.2 percent complete.

Launch nearing

During the month of April, construction completed the setting of modules three and four, and finished erecting the stick-built piperack, according to Cheniere.

Following FERC authorization to install aboveground piping and equipment on April 8, 2022, hydrocarbon piping installation has started in the stickbuilt piperack, it said.

In addition, April activities also included the completion of the upper LNG transfer arms.

Cheniere did not reveal in the update when it expects to complete the jetty. In the original schedule, the firm had expected to launch the jetty in the first quarter of 2023.

However, Cheniere said in its May investor presentation that operations of the jetty could start by the end of this year.

High demand from Europe

Cheniere’s Sabine Pass and Corpus Christi plants shipped record number of LNG cargoes in the first quarter this year due to a surge in demand from Europe.

The two terminals exported in total 160 LNG cargoes, compared to 133 cargoes in the first quarter of 2020.

About 75 percent of these cargoes landed in Europe due to high prices and as European countries look to slash reliance on Russian gas.

Most Popular

Petronas takes FID on Suriname FLNG project

Malaysian energy giant Petronas and Suriname’s state-owned oil and gas company Staatsolie have taken the final investment decision on the $1.6 billion Sloanea gas field development in offshore Block 52, which includes a floating liquefied natural gas (FLNG) facility.

Shell, IRH seal LNG supply deal

IRH Global Trading, part of UAE-based IRH, has signed a term deal to buy liquefied natural gas (LNG) from a unit of UK-based LNG giant Shell.

Hudong-Zhonghua hits new LNG carrier delivery record

China’s Hudong-Zhonghua has delivered 12 large liquefied natural gas (LNG) carriers this year to date, setting a new record for the Chinese shipbuilding industry.

More News Like This

Cheniere seeks OK to begin site preparation activities for Sabine Pass LNG expansion

US LNG exporter Cheniere is seeking approval from the Federal Energy Regulatory Commission to begin initial site preparation for the planned Sabine Pass Stage 5 LNG expansion project in Louisiana.

Cheniere’s Sabine Pass LNG expansion project gets OK from FERC

The US Federal Energy Regulatory Commission (FERC) has approved Cheniere’s planned Sabine Pass Stage 5 LNG expansion project in Louisiana.

Cheniere promotes Zach Davis to president and CFO

US LNG exporting giant Cheniere has promoted Zach Davis to president and chief financial officer, effective November 12.

Cheniere in $1.2 billion senior notes offering

US LNG exporting giant Cheniere has priced its $1.2 billion offering of senior notes due in 2037.