Cheniere: third Sabine Pass jetty more than 90 percent complete

US LNG exporting giant Cheniere and compatriot engineer Bechtel have completed more than 90 percent of the third jetty project at the six-train 30 mtpa Sabine Pass facility in Louisiana.

Cheniere is adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

It will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at the plant by 180 per year.

Cheniere won approval from FERC to build the jetty in February 2020 and after that issued a notice to proceed to Bechtel.

90.3 percent complete

According to the latest construction update filed with FERC, the project was 90.3 percent complete as of May this year, against the plan of 91.6 percent. This compares to 84.2 percent in April.

Cheniere said in the update that engineering was 100 percent complete, procurement 100 percent, subcontracts 97.7 percent, while construction was 73.1 percent complete.

During the month of May, construction completed preparations for energization of the jetty
substation and successfully energized at the end of May, according to Cheniere.

The construction of the LNG trench and slope protection continued, while pipe insultation of the hydrocarbon lines started as well, the LNG producer said.

June works

During June, Cheniere plans to complete slope protection and concrete placements for LNG
trench, as well as to start system turnover from construction to CSU and to begin loop checks at the loading platform.

Cheniere did not reveal in the update when it expects to complete the jetty. In the original schedule, the firm had expected to launch the jetty in the first quarter of 2023.

However, Cheniere said in its May investor presentation that operations of the jetty could start by the end of this year.

Most Popular

Wison scores Suriname FLNG gig

China’s Wison New Energies has signed a detailed feasibility study deal for a newbuild floating liquefied natural gas (FLNG) facility in Suriname's offshore Block 52.

Eni: third phase of YPF’s Argentina LNG project requires $20 billion investment

The third phase of YPF's Argentina LNG export project would require an investment of about $20 billion, according to Eni’s COO of global natural resources, Guido Brusco.

Venture Global to introduce gas to tenth Plaquemines liquefaction block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the tenth liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

More News Like This

Cheniere to start site preparation for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere is seeking approval from the US FERC to start site preparation activities for two more midscale trains at its Corpus Christi LNG plant in Texas.

Port of Corpus Christi says Q1 LNG volumes up 12.3 percent

The US Port of Corpus Christi in Texas reported a 12.3 percent year-on-year increase in its liquefied natural gas (LNG) volumes in the first quarter of this year.

Cheniere progresses commissioning of second Corpus Christi expansion train

US LNG exporting giant Cheniere is moving forward with commissioning activities at the second train of the Corpus Christi Stage 3 expansion project in Texas following the substantial completion of the first unit.

Corpus Christi LNG expansion project 80 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 80 percent complete.