Cheniere’s third Sabine Pass jetty 96.4 percent complete

US engineer Bechtel has completed 96.4 percent of the third jetty project at Cheniere’s six-train 30 mtpa Sabine Pass LNG facility in Louisiana.

According to the latest construction update filed with FERC, the project was 96.4 percent complete as of July this year, against the plan of 97.2 percent.

Cheniere said in the update that engineering was 100 percent complete, procurement 100 percent, subcontracts 99.4 percent, while construction was 89.9 percent complete.

During the month of July, construction completed excavations for the LNG swale, vendor steel installations on the PND (tug berth) wall, and cleaning of piping lines, according to Cheniere.

Nine systems were turned over to commissioning and startup (CSU) in July, and the last hydrocarbon systems would be turned over at the beginning of August, the LNG producer said.

Also, the remaining systems would be turned over throughout the month, with the respective commissioning demonstration tests closely following, it said.

Cheniere is adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

It will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at the plant by 180 per year.

Cheniere said earlier this year that operations of the jetty could start by the end of 2022.

Besides the Sabine Pass plant, Cheniere recently took a final investment decision on Stage 3 expansion at its Corpus Christi LNG export plant in Texas.

The expansion will add about 10 mtpa to the three-train 15 mtpa Corpus Christi plant.

In addition, Cheniere’s CEO Jack Fusco recently said the company was working to add over 30 million tonnes of capacity at its Sabine Pass and Corpus Christi plants.

Most Popular

Shell wraps up acquisition of Pavilion Energy

UK-based LNG giant Shell has completed its previously announced acquisition of Singapore's Pavilion Energy.

India’s ONGC approves Mozambique LNG investment

India’s state-run ONGC has approved an investment by its unit, ONGC Videsh, into the TotalEnergies-led Mozambique LNG joint venture, which is developing a 12.8 mtpa liquefaction plant at the Afungi complex.

Australia’s Viva Energy seeks FSRU for Geelong project

Australia’s Viva Energy is looking to secure a floating storage and regasification Unit (FSRU) for its proposed LNG import terminal in Geelong, Australia.

More News Like This

Cheniere ships 4,000th LNG cargo

US LNG exporting giant Cheniere has produced and exported the 4,000th cargo of liquefied natural gas from its Sabine Pass and Corpus Christi terminals since 2016.

Cheniere completes first train at Corpus Christi expansion project

US LNG exporting giant Cheniere has achieved substantial completion of the first liquefaction train at the Corpus Christi Stage 3 expansion project in Texas.

Cheniere gets FERC OK for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere has received approval from the US FERC to build two more midscale trains at its Corpus Christi LNG plant in Texas.

Corpus Christi LNG expansion project 78.3 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 78.3 percent complete.