Construction progress continues on Golden Pass LNG export terminal

QatarEnergy and ExxonMobil are moving forward with the construction of their Golden Pass LNG export terminal on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mpta and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the three the trains next to the existing LNG import terminal.

“Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water
protection, levee construction, stockpiling of material, and piling,” Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC.

QatarEnergy and ExxonMobil update on Golden Pass LNG work
Ground flares (Image: Golden Pass)

First LNG train expected to go online in 2024

Golden Pass and its contractors progressed installation of piping and steel in process areas, continued walls and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass continued fin fan installation in the Train 1 main piperack and progressed setting various vessels on respective foundations and continued preparatory activities for Brownfield tie-ins and LNG tanks top modifications scope.

The firm said that structural steel installation continued around the brownfield boil-off gas compressors, while it is also preparing equipment insulation in condensate area.

QatarEnergy and ExxonMobil update on Golden Pass LNG work
Brownfield 6200 piperack (Image: Golden Pass)

As per the pipeline expansion project, Golden Pass continued civil and construction activities supporting milepost (MP)01 compressor station, Sabine Spur, Natural Gas Pipeline (NGPL) Interconnect improvements, and associated facilities.

It also continued mobilization and civil activities at the MP33 and MP69 compressor station areas.

FERC said in an inspection report last month that the anticipated in-service timing for the first train is the first quarter of 2024, the third quarter of 2024 for the second train, and the first quarter of 2025 for the third train.

Most Popular

Worley gets full notice to proceed on first phase of CP2 LNG project

Australian engineering firm Worley has received a full notice to proceed from US LNG exporter Venture Global LNG under its reimbursable EPC contract for the first phase of the CP2 LNG project in Louisiana.

Venture Global’s Plaquemines LNG to commission fourth tank

US LNG exporter Venture Global LNG has received approval from the US FERC to commission the fourth storage tank with LNG at its Plaquemines plant in Louisiana.

MOL’s LNG carrier fleet stands at 104 vessels

MOL's large fleet of liquefied natural gas (LNG) tankers had 104 vessels as of the end of June this year.

More News Like This

Knutsen takes delivery of QatarEnergy LNG carrier

Norwegian shipowner Knutsen has taken delivery of another 174,000-cbm liquefied natural gas (LNG) carrier built as part of the massive QatarEnergy shipbuilding program.

Golden Pass LNG gets new FERC approval as commissioning progresses

Golden Pass LNG, a joint venture owned by energy giants QatarEnergy and ExxonMobil, is moving forward with commissioning activities at its two-train LNG plant in Texas with a new approval from the US FERC.

QatarEnergy LNG carrier wraps up trials in China

A 174,000-cubic-meter liquefied natural gas (LNG) carrier, built as part of QatarEnergy's massive shipbuilding program, has completed its trials in China, according to Hudong-Zhonghua.

Santos inks LNG supply deal with QatarEnergy’s trading unit

Australian LNG player Santos has signed a mid-term LNG supply deal with QatarEnergy Trading, a unit of state-owned LNG giant QatarEnergy.