Construction progress continues on Golden Pass LNG export terminal

QatarEnergy and ExxonMobil are moving forward with the construction of their Golden Pass LNG export terminal on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mpta and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the three the trains next to the existing LNG import terminal.

“Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water
protection, levee construction, stockpiling of material, and piling,” Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC.

QatarEnergy and ExxonMobil update on Golden Pass LNG work
Ground flares (Image: Golden Pass)

First LNG train expected to go online in 2024

Golden Pass and its contractors progressed installation of piping and steel in process areas, continued walls and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass continued fin fan installation in the Train 1 main piperack and progressed setting various vessels on respective foundations and continued preparatory activities for Brownfield tie-ins and LNG tanks top modifications scope.

The firm said that structural steel installation continued around the brownfield boil-off gas compressors, while it is also preparing equipment insulation in condensate area.

QatarEnergy and ExxonMobil update on Golden Pass LNG work
Brownfield 6200 piperack (Image: Golden Pass)

As per the pipeline expansion project, Golden Pass continued civil and construction activities supporting milepost (MP)01 compressor station, Sabine Spur, Natural Gas Pipeline (NGPL) Interconnect improvements, and associated facilities.

It also continued mobilization and civil activities at the MP33 and MP69 compressor station areas.

FERC said in an inspection report last month that the anticipated in-service timing for the first train is the first quarter of 2024, the third quarter of 2024 for the second train, and the first quarter of 2025 for the third train.

Most Popular

CEO: TotalEnergies looking to restart Mozambique LNG by end of 2024

Pouyanne discussed the Mozambique LNG project during TotalEnergies’ strategy and outlook presentation in New York on Wednesday. According to the...

Tellurian shareholders approve merger with Woodside

Tellurian said in a statement on Friday that its stockholders have approved the merger agreement proposal. The agreement was approved...

ExxonMobil picks Chart’s liquefaction tech for Rovuma LNG project

ExxonMobil picked Chart on behalf of Mozambique Rovuma Venture (MRV), which includes Italy's Eni and China's CNPC. The LNG project...

More News Like This

ExxonMobil picks Chart’s liquefaction tech for Rovuma LNG project

ExxonMobil picked Chart on behalf of Mozambique Rovuma Venture (MRV), which includes Italy's Eni and China's CNPC. The LNG project...

McDermott scores NFS gig from QatarEnergy LNG

McDermott announced the engineering, procurement, construction, and installation (EPCI) contract in a statement on Thursday. The company did not provide...

China’s Hudong-Zhonghua hits LNG carrier delivery record

China's Hudong-Zhonghua has delivered three large liquefied natural gas (LNG) carriers in September, setting a new record for the...

McDermott, partners bag Rovuma LNG FEED contract

McDermott released a statement on Tuesday revealing the FEED award for the Rovuma LNG Phase 1 project, a joint...