Fluor and JGC move one step closer to completion of LNG Canada’s first train

US engineer Fluor announced completion of the final weld on the first production train at the Shell-led LNG Canada project in Kitimat, British Columbia.

Fluor said in a statement this marks a “pivotal moment” in the construction of one of the largest energy projects in Canadian history.

The final weld took 48 hours of continuous work from teams of welders working in shifts, while more than 380 pipe welders have worked on the project since construction began in 2018, it said.

Japan’s JGC and Fluor make up the JGC-Fluor joint venture, which is delivering multiple aspects of the LNG Canada project, including engineering, procurement, fabrication and delivery of modules, as well as construction of the project’s infrastructure and utilities, marine structures, and one 225,000-cbm LNG storage tank.

LNG Canada is a joint venture between operator Shell, Petronas, PetroChina, Mitsubishi Corporation, and Kogas.

The two-train project will have an initial capacity to produce 12.7 metric tonnes (14 million tons) of LNG per year with first shipment expected by the middle of 2025, Fluor said.

Fluor did not provide information regarding the commissioning of the facility.

Malaysia’s Petronas said on Monday that the facility is slated for start-up in the latter part of 2024.

Earlier this year, Shell’s CEO, Wael Sawan, said that the LNG Canada terminal is more than 90 percent complete and the project is preparing to launch commissioning activities later this year.

LNG Canada said in the December 2023 update that that it expects start-up activities to last more than a year.

This is the first large LNG export terminal in Canada, while the project partners are also considering a second phase.

Last year, TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the LNG Canada terminal, was mechanically completed.

Most Popular

MAN will no longer offer ME-GA engine

Volkswagen’s MAN unveiled the ME-GA dual-fuel engine in March 2021, describing it as an Otto-cycle variant of the company’s...

Kumul awards pre-FEED contract to Wison for Papua New Guinea’s first FLNG

The two firms signed the contract on Friday. With an expected capacity of 1.5 mtpa, Papua New Guinea’s first FLNG...

Atlantic LNG shipping rates dip to $26,750 per day

Last week, Atlantic LNG shipping rates dropped below $50,000 per day. “Spark30S Atlantic rates dropped for a fourth consecutive week,...

More News Like This

Shell’s LNG Canada starts cooldown activities

LNG Canada previously said it would receive a cargo of refrigerants (liquefied petroleum gas) onboard the tanker Gaschem Atlantic. The...

First Gen’s Batangas FSRU gets new LNG cargo

The 162,000-cbm FSRU BW Batangas, owned by BW LNG and chartered by First Gen, received the cargo from the...

KBR bags Manatee gig from Shell

US engineer KBR has secured a contract from LNG giant Shell for the onshore portion of the latter’s Manatee...

Shell expects Q3 LNG trading results to be in line compared to previous quarter

Shell revealed this in its third-quarter update note on Monday. The company’s adjusted earnings reached $6.29 billion in the second...