Golden Pass LNG to ramp up construction activities after Zachry deal

QatarEnergy and ExxonMobil will ramp up construction activities at the Golden Pass LNG export terminal in Texas after a bankruptcy court approved a settlement agreement with Zachry Holdings.

State-owned QatarEnergy owns a 70 percent stake in the three-train Golden Pass LNG project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott’s CB&I, and Zachry won the contract to build the tree Golden Pass trains worth more than $10 billion next to the existing LNG import terminal.

However, Zachry said on May 21 it has filed for bankruptcy, initiating a structured exit from the Golden Pass LNG export project due to “financial challenges” related to the construction of the facility.

Japan’s Chiyoda said in a statement that Golden Pass LNG has filed motions on June 18 requesting Zachry’s withdrawal from the project and for lifting the automatic stay to resume construction work of the first train.

Dispute resolved

Zachry Holdings said on Wednesday in a statement that that the U.S. Bankruptcy Court for the Southern District of Texas has approved its settlement agreement with Golden Pass and joint venture partners CB&I and Chiyoda International.

“The comprehensive settlement agreement fully resolves all financial and legal disputes among the parties related to the Golden Pass export terminal project in Sabine Pass, Texas,” it said.

Also, the settlement allows Golden Pass to resume construction on an “expedited basis” while Zachry will exit the project in an “efficient and cooperative manner”, the company said.

The settlement, which has been approved by the court on an interim basis, creates a path for ZHI to complete its court-supervised restructuring process on an “expedited basis”, it added.

Golden Pass “focused on getting people back to work”

Golden Pass told LNG Prime in an emailed statement the company “acknowledges the court’s approval of the interim order associated with Zachry Holdings, Inc.’s motion in bankruptcy court.”

“This allows Golden Pass and our construction contractors McDermott and Chiyoda to ramp up site construction activities and progress our LNG terminal,” the company said

“Going forward, we are focused on getting people back to work, including local workers and vendors, and progressing this critical energy project. We are committed to a safe and successful completion of this world class facility,” the company said.

Golden Pass did not say when it expects to launch LNG production and complete the terminal.

The JV recently said that the project is 75 percent complete.

Golden Pass recently sought approval from the FERC to increase the peak workforce to speed up the construction of the pipeline project.

According to a recent report by the FERC, the anticipated in-service timing for the pipeline expansion project is expected “sometime in the first half of 2025”.

The regulator said in a previous report that the anticipated in-service timing for the pipeline expansion project “is expected sometime prior to the second half of 2024”.

However, the FERC did not provide the timing for the liquefaction trains in the newest report.

ExxonMobil previously said that “train 1 mechanical completion is expected at the end of 2024 with first LNG in first half of 2025.”

Most Popular

BW LNG seals Jordan FSU charter deal

In addition, NEPCO will acquire ownership of the vessel at the end of the charter period, BW LNG said...

South Korea’s HD Hyundai Mipo to build LNG bunkering duo

HD Hyundai Mipo said on Thursday it will deliver these two vessels by November 2027. The vessels will have a...

Geocean completes offshore work on second Wilhelmshaven LNG terminal in Germany

French marine and offshore contractor, Geocean, a unit of VINCI Construction Grands Projets, has completed its contract awarded by...

More News Like This

ExxonMobil’s Rovuma LNG moves to FEED stage

Frank Kretschmer, president of ExxonMobil Mozambique, confirmed this via his LinkedIn account last week. "This milestone represents a crucial step...

Golden Pass seeks FERC extension to complete Texas LNG terminal

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18...

QatarEnergy seals long-term LNG supply deal with Kuwait’s KPC

QatarEnergy's CEO, Saad Sherida al-Kaabi, and KPC's CEO, Sheikh Nawaf al-Sabah, signed the SPA during a ceremony in Kuwait...

Santos CEO: Papua LNG FID expected at end of 2025

TotalEnergies has a 37.55 percent operating stake in the Papua LNG project, US-based ExxonMobil has 37.04 percent, Australia's Santos...