LNG Canada CEO: start-up activities will take more than a year to complete

Shell’s LNG Canada project is now preparing to launch start-up activities next year and this program will take more than a year to complete, according to LNG Canada’s CEO, Jason Klein.

Contractor JGC Fluor is constructing the first phase of the giant LNG Canada project that includes two liquefaction trains with a capacity of 14 mtpa in Kitimat, British Columbia.

The construction of the plant, first such terminal in Canada, was about 85 percent complete in July and during the same month LNG Canada and its contractors completed LNG tank hydro testing at the project site.

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the LNG Canada terminal, was recently mechanically completed.

Shell and its partners in the project are also evaluating the second phase of the project.

Other partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

LNG Canada CEO says start-up activities will take more than a year to complete
Image: LNG Canada

More than 85 percent complete

Klein said in LNG Canada’s 2023 year-end update the the project reached its peak construction cycle this past fall, with more than 8,000 Canadians employed at the liquefaction and export facility in Kitimat, in the traditional territory of the Haisla Nation.

He said that LNG Canada has installed all 215 of the large modules required for its gas liquefaction process and completed other critical work scopes.

“Our Kitimat facility is now more than 85 percent complete over-all,” Klein said.

“We’re now preparing for safe start-up activities to begin in 2024. That’s when our equipment is tested and fine-tuned, and we begin the process of producing LNG,” the CEO said.

Klein said that LNG Canada’s “safe start-up program will take more than a year to complete.”

“This work must be undertaken before we can start shipping our LNG abroad. We remain well-positioned to deliver our first cargoes of lower-carbon, made-in-B.C. LNG by the middle of this decade,” he said.

To date, LNG Canada and its contractors and subcontractors have awarded more than C$4.2 billion in contracts and procurement to business in British Columbia.

Of that amount, more than C$3.3 billion has been awarded to First Nations-owned businesses and local area businesses, Klein said.

Most Popular

Excelerate buys GasLog LNG carrier

US FSRU player Excelerate Energy has purchased a 2007-built steam liquefied natural gas (LNG) carrier from GasLog Partners, a part of Greek LNG shipping firm GasLog, according to brokers.

NextDecade, Bechtel agree $9 billion EPC deals for two Rio Grande LNG trains

US LNG firm NextDecade and compatriot Bechtel have finalized EPC contracts worth $9.09 billion for the construction of the fourth and fifth trains and related infrastructure at the Rio Grande LNG facility in Texas.

Worley updates on CP2 LNG work

Australian engineering firm Worley has provided an update on its reimbursable EPC contract with US LNG exporter Venture Global LNG for the latter's CP2 LNG terminal in Louisiana.

More News Like This

Shell’s LNG Canada nears first LNG

LNG giant Shell is nearing the launch of the first liquefaction train at its LNG Canada export terminal in Kitimat.

Shell takes FID on Aphrodite project to supply Trinidad’s Atlantic LNG

A unit of UK-based LNG giant Shell has taken the final investment decision for the development of the Aphrodite gas field to supply Trinidad and Tobago’s Atlantic LNG export plant.

Peru LNG terminal shipped five cargoes in May

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped five liquefied natural gas cargoes in May, two more than in the previous month.

Shell shareholders re-elect CEO Wael Sawan

Wael Sawan will continue to lead London-based LNG giant Shell following shareholder voting at the company's annual general meeting on Tuesday.