LNG Canada CEO: start-up activities will take more than a year to complete

Shell’s LNG Canada project is now preparing to launch start-up activities next year and this program will take more than a year to complete, according to LNG Canada’s CEO, Jason Klein.

Contractor JGC Fluor is constructing the first phase of the giant LNG Canada project that includes two liquefaction trains with a capacity of 14 mtpa in Kitimat, British Columbia.

The construction of the plant, first such terminal in Canada, was about 85 percent complete in July and during the same month LNG Canada and its contractors completed LNG tank hydro testing at the project site.

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the LNG Canada terminal, was recently mechanically completed.

Shell and its partners in the project are also evaluating the second phase of the project.

Other partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

LNG Canada CEO says start-up activities will take more than a year to complete
Image: LNG Canada

More than 85 percent complete

Klein said in LNG Canada’s 2023 year-end update the the project reached its peak construction cycle this past fall, with more than 8,000 Canadians employed at the liquefaction and export facility in Kitimat, in the traditional territory of the Haisla Nation.

He said that LNG Canada has installed all 215 of the large modules required for its gas liquefaction process and completed other critical work scopes.

“Our Kitimat facility is now more than 85 percent complete over-all,” Klein said.

“We’re now preparing for safe start-up activities to begin in 2024. That’s when our equipment is tested and fine-tuned, and we begin the process of producing LNG,” the CEO said.

Klein said that LNG Canada’s “safe start-up program will take more than a year to complete.”

“This work must be undertaken before we can start shipping our LNG abroad. We remain well-positioned to deliver our first cargoes of lower-carbon, made-in-B.C. LNG by the middle of this decade,” he said.

To date, LNG Canada and its contractors and subcontractors have awarded more than C$4.2 billion in contracts and procurement to business in British Columbia.

Of that amount, more than C$3.3 billion has been awarded to First Nations-owned businesses and local area businesses, Klein said.

Most Popular

Atlantic LNG shipping rates up this week

Atlantic spot LNG shipping rates increased this week, while Pacific rates dropped compared to the week before, according to Spark Commodities.

Adnoc L&S orders LNG carrier quartet in China

UAE’s Adnoc L&S, a unit of state-owned energy giant Adnoc, has ordered four liquefied natural gas (LNG) carriers from China’s Jiangnan.

US LNG exports down to 31 shipments

US liquefied natural gas (LNG) plants sent 31 cargoes during the week ending July 8, down five cargoes from the week before, according to the Energy Information Administration.
spot_img

More News Like This

Shell expects ‘significantly higher’ LNG trading results in Q2

UK-based LNG giant Shell expects trading and optimization results for its integrated gas business in the second quarter of this year to be "significantly higher" compared to the previous quarter.

Shell, PV Gas seal LNG supply deal

Petrovietnam Gas, a unit of state-owned Petrovietnam, said it had signed a five-year deal to buy LNG from a unit of UK-based LNG giant Shell.

Shell expects LNG bunkering demand to reach 45 mtpa by 2045

UK-based LNG giant Shell expects LNG bunkering demand to grow to approximately 45 million tonnes per year by 2045 as the global LNG-powered fleet continues to expand.

Shell says global LNG demand to rise 65 percent by 2050

Global demand for liquefied natural gas (LNG) is expected to increase to nearly 700 million tonnes a year by 2050, an increase of around 65 percent from 2025 levels, according to Shell’s LNG Outlook 2026.