LNG Canada CEO: start-up activities will take more than a year to complete

Shell’s LNG Canada project is now preparing to launch start-up activities next year and this program will take more than a year to complete, according to LNG Canada’s CEO, Jason Klein.

Contractor JGC Fluor is constructing the first phase of the giant LNG Canada project that includes two liquefaction trains with a capacity of 14 mtpa in Kitimat, British Columbia.

The construction of the plant, first such terminal in Canada, was about 85 percent complete in July and during the same month LNG Canada and its contractors completed LNG tank hydro testing at the project site.

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the LNG Canada terminal, was recently mechanically completed.

Shell and its partners in the project are also evaluating the second phase of the project.

Other partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

LNG Canada CEO says start-up activities will take more than a year to complete
Image: LNG Canada

More than 85 percent complete

Klein said in LNG Canada’s 2023 year-end update the the project reached its peak construction cycle this past fall, with more than 8,000 Canadians employed at the liquefaction and export facility in Kitimat, in the traditional territory of the Haisla Nation.

He said that LNG Canada has installed all 215 of the large modules required for its gas liquefaction process and completed other critical work scopes.

“Our Kitimat facility is now more than 85 percent complete over-all,” Klein said.

“We’re now preparing for safe start-up activities to begin in 2024. That’s when our equipment is tested and fine-tuned, and we begin the process of producing LNG,” the CEO said.

Klein said that LNG Canada’s “safe start-up program will take more than a year to complete.”

“This work must be undertaken before we can start shipping our LNG abroad. We remain well-positioned to deliver our first cargoes of lower-carbon, made-in-B.C. LNG by the middle of this decade,” he said.

To date, LNG Canada and its contractors and subcontractors have awarded more than C$4.2 billion in contracts and procurement to business in British Columbia.

Of that amount, more than C$3.3 billion has been awarded to First Nations-owned businesses and local area businesses, Klein said.

Most Popular

Galp wins Calcasieu Pass arbitration against Venture Global

Portuguese energy firm Galp has won an arbitration case against US LNG exporter Venture Global LNG over LNG sales from the Calcasieu Pass plant in Louisiana.

MISC to order five more LNG carriers for Petronas charter

Malaysian shipping firm MISC will order five additional newbuild 174,000-cbm liquefied natural gas (LNG) carriers at China's Hudong-Zhonghua. The vessels will serve a 20-year charter with a unit of MISC's parent, Petronas.

Seatrium scores Excelerate FSRU conversion gig

Singapore's Seatrium has secured a floating storage and regasification unit conversion contract with an option for a second contract from US FSRU player Excelerate Energy.

More News Like This

Shell: Q3 LNG trading results to be in line compared to previous quarter

UK-based LNG giant Shell expects trading and optimization results for its integrated gas business in the third quarter of 2026 to be in line compared with the previous quarter.

Peru LNG sent four shipments in September

Peru LNG’s liquefaction plant at Pampa Melchorita shipped five liquefied natural gas cargoes in September, the same as in the previous three months, according to shipment data by state-owned Perupetro.

Shell, partners take FID on LNG Canada Phase 2

UK-based LNG giant Shell and its LNG Canada partners have made a final investment decision on the project's second phase, which will double production capacity at the facility in Kitimat, British Columbia.

MET buys more US LNG from Shell

Switzerland-based energy trader MET Group has agreed to buy more US liquefied natural gas (LNG) from UK-based energy giant Shell to supply its European customers.