LNG Canada CEO: start-up activities will take more than a year to complete

Shell’s LNG Canada project is now preparing to launch start-up activities next year and this program will take more than a year to complete, according to LNG Canada’s CEO, Jason Klein.

Contractor JGC Fluor is constructing the first phase of the giant LNG Canada project that includes two liquefaction trains with a capacity of 14 mtpa in Kitimat, British Columbia.

The construction of the plant, first such terminal in Canada, was about 85 percent complete in July and during the same month LNG Canada and its contractors completed LNG tank hydro testing at the project site.

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the LNG Canada terminal, was recently mechanically completed.

Shell and its partners in the project are also evaluating the second phase of the project.

Other partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

LNG Canada CEO says start-up activities will take more than a year to complete
Image: LNG Canada

More than 85 percent complete

Klein said in LNG Canada’s 2023 year-end update the the project reached its peak construction cycle this past fall, with more than 8,000 Canadians employed at the liquefaction and export facility in Kitimat, in the traditional territory of the Haisla Nation.

He said that LNG Canada has installed all 215 of the large modules required for its gas liquefaction process and completed other critical work scopes.

“Our Kitimat facility is now more than 85 percent complete over-all,” Klein said.

“We’re now preparing for safe start-up activities to begin in 2024. That’s when our equipment is tested and fine-tuned, and we begin the process of producing LNG,” the CEO said.

Klein said that LNG Canada’s “safe start-up program will take more than a year to complete.”

“This work must be undertaken before we can start shipping our LNG abroad. We remain well-positioned to deliver our first cargoes of lower-carbon, made-in-B.C. LNG by the middle of this decade,” he said.

To date, LNG Canada and its contractors and subcontractors have awarded more than C$4.2 billion in contracts and procurement to business in British Columbia.

Of that amount, more than C$3.3 billion has been awarded to First Nations-owned businesses and local area businesses, Klein said.

- Advertisements -

Most Popular

Technip Energies CEO: Eni’s Coral Norte FLNG has ‘potential’ for FID in 2024

Eni's second floating LNG production project in Mozambique has "potential" for a final investment decision in 2024, according to...

Commonwealth LNG pushes back FID to H1 2025

Commonwealth LNG has postponed a final investment decision on its 9.3 mtpa LNG facility in Cameron, Louisiana. According to Commonwealth...

NFE expects to launch Altamira LNG production in March

US LNG firm New Fortress Energy expects to start production of liquefied natural gas at its first FLNG project...

More News Like This

CNOOC’s Zhejiang LNG terminal gets 600th cargo

CNOOC's Ningbo LNG import facility in the Chinese province of Zhejiang has received the 600th cargo of liquefied natural...

FueLNG helps in commissioning of Seatrium’s floating lab

Singapore’s FueLNG, a joint venture consisting of Shell and Seatrium, has completed the gassing up and cooling down and...

Venture Global seeks more time to complete Calcasieu Pass LNG terminal

US LNG exporter Venture Global LNG has requested more time from the US FERC to complete the commissioning of...

Shell: global LNG demand to rise more than 50 percent by 2040

Global demand for liquefied natural gas (LNG) is estimated to rise by more than 50 percent by 2040, as...