LNG Canada CEO: start-up activities will take more than a year to complete

Shell’s LNG Canada project is now preparing to launch start-up activities next year and this program will take more than a year to complete, according to LNG Canada’s CEO, Jason Klein.

Contractor JGC Fluor is constructing the first phase of the giant LNG Canada project that includes two liquefaction trains with a capacity of 14 mtpa in Kitimat, British Columbia.

The construction of the plant, first such terminal in Canada, was about 85 percent complete in July and during the same month LNG Canada and its contractors completed LNG tank hydro testing at the project site.

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the LNG Canada terminal, was recently mechanically completed.

Shell and its partners in the project are also evaluating the second phase of the project.

Other partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

LNG Canada CEO says start-up activities will take more than a year to complete
Image: LNG Canada

More than 85 percent complete

Klein said in LNG Canada’s 2023 year-end update the the project reached its peak construction cycle this past fall, with more than 8,000 Canadians employed at the liquefaction and export facility in Kitimat, in the traditional territory of the Haisla Nation.

He said that LNG Canada has installed all 215 of the large modules required for its gas liquefaction process and completed other critical work scopes.

“Our Kitimat facility is now more than 85 percent complete over-all,” Klein said.

“We’re now preparing for safe start-up activities to begin in 2024. That’s when our equipment is tested and fine-tuned, and we begin the process of producing LNG,” the CEO said.

Klein said that LNG Canada’s “safe start-up program will take more than a year to complete.”

“This work must be undertaken before we can start shipping our LNG abroad. We remain well-positioned to deliver our first cargoes of lower-carbon, made-in-B.C. LNG by the middle of this decade,” he said.

To date, LNG Canada and its contractors and subcontractors have awarded more than C$4.2 billion in contracts and procurement to business in British Columbia.

Of that amount, more than C$3.3 billion has been awarded to First Nations-owned businesses and local area businesses, Klein said.

Most Popular

Construction moving forward on Golden Pass LNG terminal

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18...

Oman LNG inks SPA with Thailand’s PTT

PTT revealed the signing of the deal in a statement issued on Thursday. PTT International Trading (PTTT), a unit of...

Pilot, Seapath secure gas supply for Galveston LNG bunkering facility

The partners said in a statement Galveston LNG Bunker Port (GLBP) had entered into a gas supply agreement with...

More News Like This

Shell’s LNG Canada terminal more than 95 percent complete

Klein said in the newest project update on Thursday that 35,000-plus individual Canadians have worked on the LNG Canada...

Peru LNG terminal sent four cargoes in August

According to the shipment data by state-owned Perupetro, during August the 4.4 mtpa LNG plant sent two shipments to...

Shell seals long-term LNG supply deal with Botas

Türkiye's Energy Minister Alparslan Bayraktar announced the deal during a ceremony held in Ankara on Monday. Under the 10-year deal,...

Shell, GAIL ink LNG carrier charter deal

GAIL revealed the signing of the charter deal for one Shell LNG carrier via its social media on August...