LNG Canada more than 60 percent complete, pipeline deal reached

The Shell-led LNG Canada export project continues to progress work at the 14 mtpa plant in Kitimat in order to start production in the middle of the decade.

The giant project, worth more than $30 billion, is now more than 60 percent complete, according to LNG Canada’s mid-year update.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation and South Korea’s Kogas.

LNG Canada and its EPC contractor JGC Fluor have to date “awarded more than $3.7 billion in procurement and contracts to companies in British Columbia,” LNG Canada’s new CEO, Jason Klein, said in the update.

“And of that amount, almost $3 billion has been awarded to local and Indigenous companies,” he said.

Pipeline deal

TC Energy’s Coastal GasLink project, which will supply natural gas to the LNG Canada export terminal, is also continuing to progress with the construction of the pipeline in British Columbia.

Coastal GasLink said in its June update the overall progress had reached 64.2 percent, compared to about 62.4 percent in the prior month.

LNG Canada and Coastal GasLink previously said they were in commercial discussions regarding the cost and schedule for the project. Previoulsy the project had a price tag of more than C$6.6 billion.

“We’re happy to share that LNG Canada and its joint venture participants have come to a commercial resolution with Coastal GasLink to address its cost and schedule performance,” Klein said in the update.

“This positive step allows both companies to move forward with a renewed focus on ensuring the pipeline is constructed safely, within the revised cost estimate, and in time for first LNG cargo by the middle of this decade,” he said.

Klein did not provide any further information regarding the deal.

Costs nearly doubled

TC Energy said in its second-quarter report on Thursday that the pipeline now has a price tag of C$11.2 billion.

“The revised agreement allows us to continue the safe and timely execution of the 670-kilometre project which is now approximately 70 percent complete, with two of eight sections finished and expected mechanical in-service by the end of 2023,” it said.

TC Energy said funding of the increased project cost estimate would be supported by an expansion of the existing project-level credit facilities and a further equity contribution by TC Energy.

It will initially make an equity contribution to Coastal GasLink of C$1.9 billion, with no resulting change to its 35 percent ownership.

Also, the firm expects to reach mechanical in-service by the end of 2023.

“We continue to believe the project remains economically viable and subject to a final investment decision, we anticipate a potential second phase of Coastal GasLink could enhance TC Energy’s project returns,” the firm added.

Most Popular

Cheniere produces first LNG cargo at Corpus Christi expansion project

US LNG exporting giant Cheniere has produced the first cargo at the Corpus Christi Stage 3 expansion project in Texas.

Centrica seals LNG supply deal with Petrobras

UK-based energy firm Centrica has signed a 15-year LNG supply deal with Brazil’s state-owned energy firm Petrobras.

Japan’s Japex boosts LNG sales

Japan Petroleum Exploration (Japex) boosted its sales of liquefied natural gas (LNG) in the April-December period last year.

More News Like This

Venture Global says to launch Calcasieu Pass LNG commercial ops in April

US LNG exporter Venture Global LNG expects to launch commercial operations at its Calcasieu Pass LNG terminal in Louisiana in April, some 68 months from its final investment decision and 38 months after production start.

BP chief expects ruling on Venture Global dispute later this year

BP's CEO Murray Auchincloss expects a ruling on an arbitration dispute with US LNG exporter Venture Global LNG to be delivered in the second half of this year.

Shell expects significant near-term LNG demand growth

UK-based LNG giant Shell expects significant LNG demand growth in the near term, fueled by ongoing projects in Qatar and the USA, according to a new report.

Peru LNG terminal sent three cargoes in January

According to the shipment data by state-owned Perupetro, during January, the 4.4 mtpa LNG plant sent two shipments to...