LNG Canada pipeline 83 percent done

TC Energy’s Coastal GasLink is moving forward with the construction work on the giant pipeline that will supply natural gas to the Shell-led LNG Canada export terminal in order to complete it by the end of this year.

Coastal GasLink said in a construction update on Thursday that the overall progress on the 670 kilometers long pipeline had reached 83 percent completion as of the end of December.

This compares to 81.2 percent completion at the end of November.

According to Coastal GasLink, there were 5,578 workers across the project route as of December 18, 2022.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023 but the costs will significantly rise.

In July last year, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said in November that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

LNG Canada 80 percent complete

As per the LNG Canada plant in Kitimat, the C$40 billion project is 80 percent complete, according to a recent statement by LNG Canada.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

The company is also planning a second stage of the project as well.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Seapeak books $19.3 million charge as it lays off seafarers on steam LNG carriers

Stonepeak’s Seapeak booked $19.3 million of restructuring charges in the second quarter of this year, primarily due to laying off its Spanish seafarers working on steam LNG carriers.

Golar moving forward with new FLNG order

Floating LNG player Golar LNG is moving forward with its plans to order its fourth FLNG conversion. In order to secure "attractive" delivery, Golar plans to enter into slot reservations for long-lead equipment within the third quarter of this year.

Hanwha’s units, Kospo to jointly buy US LNG

South Korea's Hanwha Aerospace and Hanwha Energy, units of Hanwha, are teaming up with compatriot Korea Southern Power (Kospo) to jointly buy US liquefied natural gas (LNG) supplies.

More News Like This

Fluor, JGC score FEED job for LNG Canada expansion

A joint venture of US engineer Fluor and Japan's JGC has been awarded the contract to update the front-end engineering and design (FEED) for a proposed Phase 2 expansion of the Shell-led LNG Canada project.

Shell CEO says LNG Canada ramp-up in line with expectations

LNG Canada's production ramp-up is "very much" in line with what Shell had expected, according to Shell CEO Wael Sawan.

South Korea gets first LNG Canada cargo

The 174,000-cbm GasLog Glasgow, which is carrying the first liquefied natural gas cargo produced at the Shell-led LNG Canada facility in Kitimat, has arrived in Tongyeong, South Korea, according to shipping data.

LNG Canada to send third cargo

Shell-led LNG Canada is expected to soon ship the third cargo of liquefied natural gas from the Kitimat facility, according to shipping data.