LNG Canada pipeline 83 percent done

TC Energy’s Coastal GasLink is moving forward with the construction work on the giant pipeline that will supply natural gas to the Shell-led LNG Canada export terminal in order to complete it by the end of this year.

Coastal GasLink said in a construction update on Thursday that the overall progress on the 670 kilometers long pipeline had reached 83 percent completion as of the end of December.

This compares to 81.2 percent completion at the end of November.

According to Coastal GasLink, there were 5,578 workers across the project route as of December 18, 2022.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023 but the costs will significantly rise.

In July last year, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said in November that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

LNG Canada 80 percent complete

As per the LNG Canada plant in Kitimat, the C$40 billion project is 80 percent complete, according to a recent statement by LNG Canada.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

The company is also planning a second stage of the project as well.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

NFE logs $557 million net loss, continues Puerto Rico supply deal talks

US LNG player New Fortress Energy reported a net loss of $557 million in the second quarter of 2025, while it continues to negotiate a long-term gas sale agreement with PREPA to provide gas island-wide in Puerto Rico.

MOL gets OK for two LNG carrier designs with sails

Japan’s shipping giant MOL has secured approval from classification society Lloyd's Register (LR) for two liquefied natural gas (LNG) carrier designs equipped with four Wind Challenger sails.

Hanwha Ocean scores LNG carrier order

South Korea's Hanwha Ocean has secured a new contract to build one liquefied natural gas (LNG) carrier for about $252 million.

More News Like This

LNG Canada sends tenth cargo

Shell-led LNG Canada has shipped the tenth cargo of liquefied natural gas from its Kitimat facility on the west coast of Canada.

Shell’s LNG Canada seeks OK to boost export capacity

Shell-led LNG Canada is seeking approval from the Canadian energy regulator to boost its annual export capacity by 6.4 percent.

Fluor, JGC score FEED job for LNG Canada expansion

A joint venture of US engineer Fluor and Japan's JGC has been awarded the contract to update the front-end engineering and design (FEED) for a proposed Phase 2 expansion of the Shell-led LNG Canada project.

Shell CEO says LNG Canada ramp-up in line with expectations

LNG Canada's production ramp-up is "very much" in line with what Shell had expected, according to Shell CEO Wael Sawan.