LNG Canada pipeline 83 percent done

TC Energy’s Coastal GasLink is moving forward with the construction work on the giant pipeline that will supply natural gas to the Shell-led LNG Canada export terminal in order to complete it by the end of this year.

Coastal GasLink said in a construction update on Thursday that the overall progress on the 670 kilometers long pipeline had reached 83 percent completion as of the end of December.

This compares to 81.2 percent completion at the end of November.

According to Coastal GasLink, there were 5,578 workers across the project route as of December 18, 2022.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023 but the costs will significantly rise.

In July last year, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said in November that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

LNG Canada 80 percent complete

As per the LNG Canada plant in Kitimat, the C$40 billion project is 80 percent complete, according to a recent statement by LNG Canada.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

The company is also planning a second stage of the project as well.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Indonesia’s Sillo Maritime buys LNG carrier for $65 million

Indonesia's Sillo Maritime has purchased a 2009-built liquefied natural gas (LNG) carrier for $65 million.

Ksi Lisims LNG inks deals with First Nations

Canada's Ksi Lisims LNG, the developer of a 12 mtpa LNG project in British Columbia, has signed benefits agreements with three First Nations.

South Korea’s Posco International, Kospo ink HoA for Gwangyang LNG terminal

Posco International, a unit of South Korean steel producer Posco, and Korea Southern Power (Kospo) have signed a heads of agreement on the use of Posco International's Gwangyang LNG import terminal and the construction of a pipeline.

More News Like This

PetroVietnam Gas receives Canadian LNG cargo

PetroVietnam Gas, a unit of state-owned PetroVietnam, has received a cargo of liquefied natural gas from Canada as it increases LNG imports amid disruptions caused by the Middle East conflict.

Fluor, JGC get limited notice to proceed for LNG Canada expansion

Fluor, JGC get limited notice to proceed for LNG Canada expansion

U-Ming, K Line name LNG carrier in South Korea

Taiwan’s shipowner U-Ming Marine Transport has named the first liquefied natural gas (LNG) carrier in its fleet as part of a joint venture with Japan's shipping giant K Line.

Shell’s LNG Canada eyes Phase 2 FID by end of this year

Shell-led LNG Canada has reached a deal with the provincial and state governments to work towards a final investment decision on the planned expansion of its Kitimat LNG export facility on the west coast of Canada by the end of this year.