LNG Canada pipeline 83 percent done

TC Energy’s Coastal GasLink is moving forward with the construction work on the giant pipeline that will supply natural gas to the Shell-led LNG Canada export terminal in order to complete it by the end of this year.

Coastal GasLink said in a construction update on Thursday that the overall progress on the 670 kilometers long pipeline had reached 83 percent completion as of the end of December.

This compares to 81.2 percent completion at the end of November.

According to Coastal GasLink, there were 5,578 workers across the project route as of December 18, 2022.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023 but the costs will significantly rise.

In July last year, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said in November that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

LNG Canada 80 percent complete

As per the LNG Canada plant in Kitimat, the C$40 billion project is 80 percent complete, according to a recent statement by LNG Canada.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

The company is also planning a second stage of the project as well.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

TotalEnergies to transfer Papua LNG operatorship to ExxonMobil

French energy giant TotalEnergies said on Monday that Papua LNG has achieved "major" contractual and commercial milestones, marking "decisive" steps towards a final investment decision. These include completing the EPC tendering process and transferring Papua LNG operatorship to US energy giant ExxonMobil, operator of the PNG LNG project.

Gasunie, Vopak plan fifth Gate LNG jetty

Dutch partners Gasunie and Vopak plan to build a fifth liquefied natural gas (LNG) jetty at their Gate terminal in the port of Rotterdam.

Arctic LNG 2 seeks $1 billion from Hanwha Ocean over terminated LNG carrier orders

Novatek-led Arctic LNG 2 is seeking approximately $1 billion in damages from South Korean shipbuilder Hanwha Ocean over terminated shipbuilding contracts for Arc7 ice-class LNG tankers.

More News Like This

Shell CEO: LNG Canada Phase 2 FID likely by end of this year

Shell CEO Wael Sawan confirmed on Thursday that the company and its LNG Canada partners expect to take a final investment decision on the second phase of the project by the end of this year.

LNG Canada offers option to First Nations to invest in Phase 2 storage tank

Shell-led LNG Canada has signed an agreement with five northwestern B.C. First Nations, giving them the option to invest up to C$1 billion ($711 million) to acquire an LNG storage tank slated for construction as part of the expansion of its Kitimat LNG export facility on the west coast of Canada.

LNG Canada ships 100th cargo

Shell-led LNG Canada has shipped the 100th cargo of liquefied natural gas from its Kitimat facility on the west coast of Canada.

PetroVietnam Gas receives Canadian LNG cargo

PetroVietnam Gas, a unit of state-owned PetroVietnam, has received a cargo of liquefied natural gas from Canada as it increases LNG imports amid disruptions caused by the Middle East conflict.