LNG Canada pipeline almost 65 percent complete

TC Energy’s Coastal GasLink project, which will supply natural gas to the Shell-led LNG Canada export terminal, is continuing to progress with the construction of the pipeline in British Columbia.

Coastal GasLink said in its June update the overall progress had reached 64.2 percent, compared to about 62.4 percent in the prior month.

“The summer construction season is quickly ramping up, with more than 6000 women and men expected to work along Coastal GasLink’s project route at its peak,” it said.

In addition, Cable Crane Hill, one of the many special sections along Coastal GasLink’s 670 km route, has transported its first segment of pipe up the steep slope using the cable crane.

Coastal GasLink’s contractors are mobilizing crews to various sites along the project route to continue to progress Coastal GasLink’s “most important construction season yet”, the firm said.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat.

LNG Canada said in May it was reaching the 60 percent completion mark after it received a large module from China.

Also, the developer of the 14 mtpa LNG export plant in Kitimat earlier this year appointed Jason Klein as its new chief executive and said it remains on track to deliver its first cargo by the middle of this decade.

Besides operator Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

YPF CEO: FID on second Argentina FLNG expected by July

Pan American Energy, Golar LNG, YPF, Pampa Energia, and Harbour Energy plan to take a final investment decision on Argentina's second floating LNG production unit by the end of July, according to YPF CEO Horacio Marin.

Sempra still targets Port Arthur LNG expansion FID in 2025

Sempra Infrastructure, a unit of Sempra, still expects to make a final investment decision on the second phase of its Port Arthur LNG export project in Texas in 2025.

Germany, Egypt seal FSRU charter deal

Germany's Ministry for Economic Affairs and Energy has signed a deal with Egypt's state-owned EGAS to charter the 174,000-cbm FSRU Energos Power.

More News Like This

Peru LNG terminal shipped three cargoes in April

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped three liquefied natural gas cargoes in April due to restrictions on the transportation system, according to operator Hunt Oil.

CFO: Shell on track to ship first LNG Canada cargo in middle of 2025

LNG giant Shell remains on track to deliver the first liquefied natural gas cargo from its LNG Canada export terminal in Kitimat in the middle of this year, according to Shell's finance chief, Sinead Gorman.

Shell’s Q1 profit reaches $5.58 billion, LNG sales drop

LNG giant Shell reported a drop in adjusted earnings in the first quarter of 2025, while its LNG sales also decreased compared to the same quarter in 2024.

Venture Global launches Calcasieu Pass LNG commercial ops

US LNG exporter Venture Global LNG has launched commercial operations at its Calcasieu Pass LNG terminal in Louisiana, some 68 months from its final investment decision and 38 months after production start.