LNG Canada pipeline almost 75 percent complete

TC Energy’s Coastal GasLink project, which will supply natural gas to the Shell-led LNG Canada export terminal, continues to progress with the construction of the pipeline in British Columbia.

Coastal GasLink said in a statement on September 20 announcing the completion of its Wilde Lake compressor facility that the pipeline has approached 75 percent overall completion. The overall progress reached 69 percent as of the end of July.

According to the firm, the Wilde Lake facility near Dawson Creek in northeastern BBC would serve as the starting point for the natural gas pipeline, compressing the gas to provide the pressure required to safely deliver the gas all the way to LNG Canada’s site in Kitimat.

It has the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023.

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Eni: third phase of YPF’s Argentina LNG project requires $20 billion investment

The third phase of YPF's Argentina LNG export project would require an investment of about $20 billion, according to Eni’s COO of global natural resources, Guido Brusco.

Wison scores Suriname FLNG gig

China’s Wison New Energies has signed a detailed feasibility study deal for a newbuild floating liquefied natural gas (FLNG) facility in Suriname's offshore Block 52.

Venture Global to introduce gas to tenth Plaquemines liquefaction block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the tenth liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

More News Like This

Venture Global launches Calcasieu Pass LNG commercial ops

US LNG exporter Venture Global LNG has launched commercial operations at its Calcasieu Pass LNG terminal in Louisiana, some 68 months from its final investment decision and 38 months after production start.

YPF expects more supermajors to join Argentina LNG project, CEO says

Argentina’s state-owned oil and gas company YPF expects more supermajors to become equity partners in the planned Argentina LNG project following a deal with Shell, according to CEO Horacio Marin.

Shell expects Q1 LNG trading results to be in line compared to previous quarter

LNG giant Shell expects trading and optimization results for its integrated gas business in the first quarter of this year to be in line compared with the fourth quarter of last year.

Peru LNG terminal sent five shipments in March

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped five liquefied natural gas cargoes in March, one more than in the previous month.