QatarEnergy and ExxonMobil provide update on Golden Pass LNG construction

QatarEnergy and ExxonMobil released the latest construction update for their giant Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas, as they work to launch the first train next year.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

Work progressing

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water protection, levee construction, stockpiling of material, and piling.

Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas, continued piping and vessels insulation activities and helical piles and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins.

The firm also continued LNG tank tops modifications and progressed cable tray installations and cable pulling activities, and continued pipe pneumatic/hydrostatic testing program.

QatarEnergy and ExxonMobil Golden Pass LNG
Brownfield storage tanks/piperacks (Image: Golden Pass)

As per the pipeline expansion project, Golden Pass continued civil and construction activities supporting milepost (MP)01 Compressor Station, Sabine Spur, Natural Gas Pipeline (NGPL) Interconnect improvements, and associated facilities.

Nitrogen system

Golden Pass recently also submitted its implementation plan No. 242 to the FERC to provide information needed prior to commissioning and introduction of hazardous fluids for the nitrogen system (961).

Also, the company requests authorization of the implementation plan to allow it to begin the commissioning and startup of the nitrogen system by November 10, 2023.

As per the start of operations, the FERC said in an inspection report on August 30 that the anticipated in-service timing for the first Golden Pass train is the second half of 2024, with the second and the third train following after.

Most Popular

Venture Global files for IPO, plans to boost LNG export capacity to 104 mtpa

According to an SEC filing, Venture Global plans to list its Class A common shares under the symbol "VG"...

Germany’s DET offers short-term regas capacity at two LNG terminals

DET announced on Thursday the marketing of short-term regasification capacities at its FSRU-based LNG terminals in Brunsbüttel and Wilhelmshaven...

Swan Energy, Nebula’s AG&P LNG plan Indian JV

Swan Energy said on Friday it had signed a heads of agreement with AG&P Terminals &Logistics (Singapore). The two firms...

More News Like This

Chevron-led JV secures GHG permit near Barrow Island

US energy giant Chevron and its partners Shell and ExxonMobil have been awarded the greenhouse gas (GHG) assessment permit...

ExxonMobil’s LNG sales to grow beyond 40 mtpa by 2030

ExxonMobil just announced its corporate plan to 2030 saying it expects to deliver incremental growth potential of $20 billion...

QatarEnergy completes massive LNG shipbuilding program

QatarEnergy said on Wednesday it has selected the joint venture of MOL (MOL) and Cosco Shipping LNG Investment (Shanghai)...

Cosco Shipping, MOL team up on six QC-Max LNG carriers

Shanghai Cosco Shipping LNG Investment, a unit of CSET, will take a 50 percent stake in each of the...