QatarEnergy and ExxonMobil provide update on Golden Pass LNG construction

QatarEnergy and ExxonMobil released the latest construction update for their giant Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas, as they work to launch the first train next year.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

Work progressing

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water protection, levee construction, stockpiling of material, and piling.

Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas, continued piping and vessels insulation activities and helical piles and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins.

The firm also continued LNG tank tops modifications and progressed cable tray installations and cable pulling activities, and continued pipe pneumatic/hydrostatic testing program.

QatarEnergy and ExxonMobil Golden Pass LNG
Brownfield storage tanks/piperacks (Image: Golden Pass)

As per the pipeline expansion project, Golden Pass continued civil and construction activities supporting milepost (MP)01 Compressor Station, Sabine Spur, Natural Gas Pipeline (NGPL) Interconnect improvements, and associated facilities.

Nitrogen system

Golden Pass recently also submitted its implementation plan No. 242 to the FERC to provide information needed prior to commissioning and introduction of hazardous fluids for the nitrogen system (961).

Also, the company requests authorization of the implementation plan to allow it to begin the commissioning and startup of the nitrogen system by November 10, 2023.

As per the start of operations, the FERC said in an inspection report on August 30 that the anticipated in-service timing for the first Golden Pass train is the second half of 2024, with the second and the third train following after.

Most Popular

Venture Global’s Plaquemines LNG seals new gas supply deal

Venture Global LNG’s Plaquemines LNG has signed a new natural gas sale and purchase deal with gas marketer Tenaska Marketing Ventures, according to a DOE filing.

TotalEnergies working on Mozambique LNG restart, CEO says

France's TotalEnergies and its partners in the giant Mozambique LNG project are still working with the Mozambique government on restarting construction on the 12.8 mtpa project, according to Patrick Pouyanne, CEO of TotalEnergies.

Shell takes FID on Egypt gas project

A unit of UK-based LNG giant Shell has taken the final investment decision for the development of the Mina West gas discovery in Egypt’s Mediterranean Sea.

More News Like This

Golden Pass LNG gets new FERC approval as commissioning progresses

Golden Pass LNG, a joint venture owned by energy giants QatarEnergy and ExxonMobil, is moving forward with commissioning activities at its two-train LNG plant in Texas with a new approval from the US FERC.

QatarEnergy LNG carrier wraps up trials in China

A 174,000-cubic-meter liquefied natural gas (LNG) carrier, built as part of QatarEnergy's massive shipbuilding program, has completed its trials in China, according to Hudong-Zhonghua.

Santos inks LNG supply deal with QatarEnergy’s trading unit

Australian LNG player Santos has signed a mid-term LNG supply deal with QatarEnergy Trading, a unit of state-owned LNG giant QatarEnergy.

Golden Pass LNG seeks re-export approval

Golden Pass LNG, a joint venture owned by energy giants QatarEnergy and ExxonMobil, is seeking approval from the US DOE to export previously imported LNG from October, as it nears the launch of the first liquefaction train.