QatarEnergy and ExxonMobil provide update on Golden Pass LNG construction

QatarEnergy and ExxonMobil released the latest construction update for their giant Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas, as they work to launch the first train next year.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

Work progressing

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water protection, levee construction, stockpiling of material, and piling.

Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas, continued piping and vessels insulation activities and helical piles and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins.

The firm also continued LNG tank tops modifications and progressed cable tray installations and cable pulling activities, and continued pipe pneumatic/hydrostatic testing program.

QatarEnergy and ExxonMobil Golden Pass LNG
Brownfield storage tanks/piperacks (Image: Golden Pass)

As per the pipeline expansion project, Golden Pass continued civil and construction activities supporting milepost (MP)01 Compressor Station, Sabine Spur, Natural Gas Pipeline (NGPL) Interconnect improvements, and associated facilities.

Nitrogen system

Golden Pass recently also submitted its implementation plan No. 242 to the FERC to provide information needed prior to commissioning and introduction of hazardous fluids for the nitrogen system (961).

Also, the company requests authorization of the implementation plan to allow it to begin the commissioning and startup of the nitrogen system by November 10, 2023.

As per the start of operations, the FERC said in an inspection report on August 30 that the anticipated in-service timing for the first Golden Pass train is the second half of 2024, with the second and the third train following after.

Most Popular

Canada’s Cedar LNG names FLNG

Canada’s Cedar LNG, a joint venture of Canada’s Pembina Pipeline and the Haisla Nation, has picked a name for its floating LNG facility, which will be located in the traditional territory of the Haisla Nation, on Canada’s West Coast.

NextDecade, Jera seal 20-year LNG SPA

Japan's Jera has signed a 20-year deal to buy liquefied natural gas from the planned fifth train at NextDecade's Rio Grande LNG facility in Texas.

Australia’s Viva Energy gets OK for Geelong LNG import terminal

Australia’s Viva Energy has secured approval from the Victorian government for its proposed FSRU-based LNG import terminal in Geelong, Australia.

More News Like This

QatarEnergy eyes major LNG trading expansion

State-owned LNG giant QatarEnergy aims to increase trading of non-Qatari physical LNG volumes to 30 to 40 million tons by 2030, according to Qatar’s energy minister and chief executive of QatarEneergy, Saad Sherida Al-Kaabi.

China’s Hudong-Zhonghua delivers its 50th LNG carrier

Chinese shipbuilder Hudong-Zhonghua has delivered its 50th liquefied natural gas (LNG) carrier.

ExxonMobil CEO expects Golden Pass LNG launch by end of this year

ExxonMobil CEO Darren Woods expects the QatarEnergy-led Golden Pass LNG export project in Texas to produce first LNG volumes by the end of this year. Separately, Golden Pass LNG is also seeking approval from the US FERC to increase peak workforce up to 10,300.

Golden Pass LNG moving forward with commissioning activities

Golden Pass LNG, a joint venture of QatarEnergy and ExxonMobil, is moving forward with the commissioning work at its giant LNG export facility in Texas with new approval from the US FERC.