QatarEnergy and ExxonMobil provide update on Golden Pass LNG construction

QatarEnergy and ExxonMobil released the latest construction update for their giant Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas, as they work to launch the first train next year.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

Work progressing

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water protection, levee construction, stockpiling of material, and piling.

Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas, continued piping and vessels insulation activities and helical piles and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins.

The firm also continued LNG tank tops modifications and progressed cable tray installations and cable pulling activities, and continued pipe pneumatic/hydrostatic testing program.

QatarEnergy and ExxonMobil Golden Pass LNG
Brownfield storage tanks/piperacks (Image: Golden Pass)

As per the pipeline expansion project, Golden Pass continued civil and construction activities supporting milepost (MP)01 Compressor Station, Sabine Spur, Natural Gas Pipeline (NGPL) Interconnect improvements, and associated facilities.

Nitrogen system

Golden Pass recently also submitted its implementation plan No. 242 to the FERC to provide information needed prior to commissioning and introduction of hazardous fluids for the nitrogen system (961).

Also, the company requests authorization of the implementation plan to allow it to begin the commissioning and startup of the nitrogen system by November 10, 2023.

As per the start of operations, the FERC said in an inspection report on August 30 that the anticipated in-service timing for the first Golden Pass train is the second half of 2024, with the second and the third train following after.

Most Popular

Venture Global’s CP2 LNG seeks re-export approval

US LNG exporter Venture Global is seeking approval from the US DOE to export previously imported LNG from its CP2 LNG project in Louisiana, as it nears the launch of the project's first phase.

Inpex seals first Abadi LNG SPAs

Japan's Inpex has signed the first liquefied natural gas (LNG) sales and purchase agreements for the planned Abadi LNG project in Indonesia, a spokesman for Inpex confirmed to LNG Prime on Thursday.

Seapeak inks sale and leaseback deal for LNG carrier duo

Stonepeak’s Seapeak has signed a sale and leaseback deal for two liquefied natural gas (LNG) carriers that are currently being built at South Korea's Samsung Heavy Industries.

More News Like This

Orlen terminates QatarEnergy LNG supply contract

Poland’s Orlen said it had exercised its right to terminate one of the two long-term LNG supply contracts with a unit state-owned LNG giant QatarEnergy due to an ongoing force majeure resulting in an inability to meet contractual delivery obligations.

ExxonMobil boosts Rovuma LNG stake

US energy giant ExxonMobil has increased its stake in the planned Rovuma LNG project in Mozambique through a deal with Italy's Eni, while the company still targets a final investment decision by the end of this year, according to ExxonMobil CEO Darren Woods.

Technip Energies ready to hand over first NFE LNG train to QatarEnergy

French LNG engineer Technip Energies is ready to hand over the first train of the North Field East LNG project in Qatar to state-owned LNG giant QatarEnergy, while the second train has already started commissioning, according to Technip Energies CEO Arnaud Pieton.

Nakilat says no one injured after LNG carrier attack

Qatari LNG shipping giant Nakilat said that no one was injured after its 266,000-cbm Q-Max LNG carrier Al Mayeda was hit by "unidentified objects" while transiting the Arabian Gulf on Friday evening.