QatarEnergy and ExxonMobil provide update on Golden Pass LNG construction

QatarEnergy and ExxonMobil released the latest construction update for their giant Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas, as they work to launch the first train next year.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

Work progressing

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water protection, levee construction, stockpiling of material, and piling.

Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas, continued piping and vessels insulation activities and helical piles and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins.

The firm also continued LNG tank tops modifications and progressed cable tray installations and cable pulling activities, and continued pipe pneumatic/hydrostatic testing program.

QatarEnergy and ExxonMobil Golden Pass LNG
Brownfield storage tanks/piperacks (Image: Golden Pass)

As per the pipeline expansion project, Golden Pass continued civil and construction activities supporting milepost (MP)01 Compressor Station, Sabine Spur, Natural Gas Pipeline (NGPL) Interconnect improvements, and associated facilities.

Nitrogen system

Golden Pass recently also submitted its implementation plan No. 242 to the FERC to provide information needed prior to commissioning and introduction of hazardous fluids for the nitrogen system (961).

Also, the company requests authorization of the implementation plan to allow it to begin the commissioning and startup of the nitrogen system by November 10, 2023.

As per the start of operations, the FERC said in an inspection report on August 30 that the anticipated in-service timing for the first Golden Pass train is the second half of 2024, with the second and the third train following after.

- Advertisements -

Most Popular

Chevron working to resume full Gorgon LNG production after ‘mechanical fault’

Chevron Australia, a unit of US energy giant Chevron, is working to resume full production from its Gorgon LNG...

Commissioning of India’s Chhara LNG terminal delayed

India’s Hindustan Petroleum, a unit of state-owned ONGC, has reportedly delayed the commissioning of its Chhara LNG import terminal...

Tellurian’s net loss widens in Q1, Driftwood LNG talks continue

US LNG firm Tellurian reported a widening first-quarter loss on Thursday, as it continues to work to secure financing...

More News Like This

QatarEnergy seals $6 billion deal with Chinese shipbuilder for 18 giant LNG carriers

State-owned LNG giant QatarEnergy has signed a major shipbuilding deal worth $6 billion with China State Shipbuilding Corp for...

Papua New Guinea’s Kumul sells its first spot LNG cargo

Papua New Guinea’s national oil and gas company Kumul Petroleum said it had sold its first spot liquefied natural...

GTT secures LNG tank gig for eight vessels

French LNG containment giant GTT has secured a tank design order for eight 174,000-cbm LNG carriers. GTT said a statement...

PetroVietnam Gas: Thi Vai terminal receives second LNG cargo

PetroVietnam Gas, a unit of state-owned PetroVietnam, has received the second liquefied natural gas cargo at its Thi Vai...