QatarEnergy and ExxonMobil update on Golden Pass LNG work

QatarEnergy and ExxonMobil continue to make progress in building their $10 billion Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mpta and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the trains next to the existing LNG import terminal.

“Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water
protection, levee construction, stockpiling of material, and piling,” Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC.

QatarEnergy and ExxonMobil update on Golden Pass LNG work
Brownfield piperack (Image: Golden Pass)

First train in 2024

Golden Pass and its contractors progressed installation of piping and steel in process areas, continued walls and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass continued fin fan installation in the Train 1 main piperack and progressed setting various vessels on respective foundations and continued preparatory activities for Brownfield tie-ins and LNG tanks top modifications scope.

The firm said that structural steel installation continued around the brownfield boil-off gas compressors.

According to Golden Pass, it started precommissioning activities as well.

As per the pipeline expansion project, Golden Pass continued construction activities for the new 24-inch-diameter Sabine pipeline spur, and started mobilization and civil activities at the milepost (MP) 33 and MP69 compressor station areas.

FERC said in an inspection report last month that the anticipated in-service timing for the first train is the first quarter of 2024, the third quarter of 2024 for the second train, and the first quarter of 2025 for the third train.

Most Popular

Trio gets OK for $3.3 billion LNG-to-power deal in Philippines

According to separate statements by the firms, the Philippine Competition Commission (PCC) has approved the joint acquisition of two...

UAE’s Adnoc, Thailand’s Gulf ink LNG supply deal

State-owned Adnoc said on Monday that Adnoc Trading's LNG desk has recently signed a supply agreement with Thaliand's Gulf...

Golar takes full ownership of FLNG Hilli

Golar announced on Monday it had acquired Seatrium’s and Black & Veatch’s minority ownership interests in the FLNG, which...

More News Like This

Chevron-led JV secures GHG permit near Barrow Island

US energy giant Chevron and its partners Shell and ExxonMobil have been awarded the greenhouse gas (GHG) assessment permit...

ExxonMobil’s LNG sales to grow beyond 40 mtpa by 2030

ExxonMobil just announced its corporate plan to 2030 saying it expects to deliver incremental growth potential of $20 billion...

QatarEnergy completes massive LNG shipbuilding program

QatarEnergy said on Wednesday it has selected the joint venture of MOL (MOL) and Cosco Shipping LNG Investment (Shanghai)...

Cosco Shipping, MOL team up on six QC-Max LNG carriers

Shanghai Cosco Shipping LNG Investment, a unit of CSET, will take a 50 percent stake in each of the...