QatarEnergy and ExxonMobil update on Golden Pass LNG work

QatarEnergy and ExxonMobil continue to make progress in building their $10 billion Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mpta and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the trains next to the existing LNG import terminal.

“Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water
protection, levee construction, stockpiling of material, and piling,” Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC.

QatarEnergy and ExxonMobil update on Golden Pass LNG work
Brownfield piperack (Image: Golden Pass)

First train in 2024

Golden Pass and its contractors progressed installation of piping and steel in process areas, continued walls and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass continued fin fan installation in the Train 1 main piperack and progressed setting various vessels on respective foundations and continued preparatory activities for Brownfield tie-ins and LNG tanks top modifications scope.

The firm said that structural steel installation continued around the brownfield boil-off gas compressors.

According to Golden Pass, it started precommissioning activities as well.

As per the pipeline expansion project, Golden Pass continued construction activities for the new 24-inch-diameter Sabine pipeline spur, and started mobilization and civil activities at the milepost (MP) 33 and MP69 compressor station areas.

FERC said in an inspection report last month that the anticipated in-service timing for the first train is the first quarter of 2024, the third quarter of 2024 for the second train, and the first quarter of 2025 for the third train.

Most Popular

Venture Global’s CP2 LNG to start mobilization and site preparation

Venture Global LNG's CP2 LNG has received approval from the US FERC to start mobilization and other limited activities for the LNG project in Louisiana.

BP seals LNG SPA with India’s Torrent Power

A unit of UK-based energy giant BP has signed a long-term liquefied natural gas (LNG) supply deal with India's Torrent Power.

Cheniere kicks off Sabine Pass LNG maintenance

US LNG exporting giant Cheniere has started planned maintenance at its Sabine Pass LNG export facility in Louisiana.

More News Like This

QatarEnergy eyes major LNG trading expansion

State-owned LNG giant QatarEnergy aims to increase trading of non-Qatari physical LNG volumes to 30 to 40 million tons by 2030, according to Qatar’s energy minister and chief executive of QatarEneergy, Saad Sherida Al-Kaabi.

China’s Hudong-Zhonghua delivers its 50th LNG carrier

Chinese shipbuilder Hudong-Zhonghua has delivered its 50th liquefied natural gas (LNG) carrier.

ExxonMobil CEO expects Golden Pass LNG launch by end of this year

ExxonMobil CEO Darren Woods expects the QatarEnergy-led Golden Pass LNG export project in Texas to produce first LNG volumes by the end of this year. Separately, Golden Pass LNG is also seeking approval from the US FERC to increase peak workforce up to 10,300.

Golden Pass LNG moving forward with commissioning activities

Golden Pass LNG, a joint venture of QatarEnergy and ExxonMobil, is moving forward with the commissioning work at its giant LNG export facility in Texas with new approval from the US FERC.