QatarEnergy and ExxonMobil update on Golden Pass LNG work

QatarEnergy and ExxonMobil continue to make progress in building their $10 billion Golden Pass LNG export plant on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mpta and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the trains next to the existing LNG import terminal.

“Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water
protection, levee construction, stockpiling of material, and piling,” Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC.

QatarEnergy and ExxonMobil update on Golden Pass LNG work
Brownfield piperack (Image: Golden Pass)

First train in 2024

Golden Pass and its contractors progressed installation of piping and steel in process areas, continued walls and piping installation for the ground flares, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass continued fin fan installation in the Train 1 main piperack and progressed setting various vessels on respective foundations and continued preparatory activities for Brownfield tie-ins and LNG tanks top modifications scope.

The firm said that structural steel installation continued around the brownfield boil-off gas compressors.

According to Golden Pass, it started precommissioning activities as well.

As per the pipeline expansion project, Golden Pass continued construction activities for the new 24-inch-diameter Sabine pipeline spur, and started mobilization and civil activities at the milepost (MP) 33 and MP69 compressor station areas.

FERC said in an inspection report last month that the anticipated in-service timing for the first train is the first quarter of 2024, the third quarter of 2024 for the second train, and the first quarter of 2025 for the third train.

- Advertisements -

Most Popular

Tellurian explores sale options, makes leadership changes

US LNG firm Tellurian, the developer of the Driftwood LNG export project in Louisiana, has made new changes to...

Venture Global says building fleet of nine LNG carriers

US LNG exporter Venture Global LNG said on Sunday it has nine liquefied natural gas carriers on order in...

US LNG exports reach 26 shipments

US liquefied natural gas (LNG) exports rose in the week ending March 13 compared to the week before, according...

More News Like This

Saipem ships North Field modules from Indonesia to Qatar

Italian contractor Saipem has shipped the first three modules from Indonesia to Qatar, where they will be installed as...

South Korea’s Hanwha Ocean inks memorandum to build 12 LNG carriers

South Korean shipbuilder Hanwha Ocean, previously known as DSME, has signed a memorandum of agreement to build 12 liquefied...

Ledwood nets South Hook LNG contract

Ledwood Mechanical Engineering won a contract from UK's South Hook LNG terminal in Milford Haven. The Pembroke Dock-based firm said...

Technip Energies CEO: Eni’s Coral Norte FLNG has ‘potential’ for FID in 2024

Eni's second floating LNG production project in Mozambique has "potential" for a final investment decision in 2024, according to...