QatarEnergy, ExxonMobil moving forward with Golden Pass LNG work

Energy giants QatarEnergy and ExxonMobil released the latest construction update for their Golden Pass LNG export terminal on the US Gulf Coast near Sabine Pass, Texas.

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18 mtpa and will offtake 70 percent of the capacity, while US energy firm ExxonMobil has a 30 percent share.

A joint venture of Chiyoda, McDermott, and Zachry is building the tree Golden Pass trains worth about $10 billion next to the existing LNG import terminal.

Golden Pass LNG Terminal and Golden Pass Pipeline said in the newest construction report filed with the US FERC that Golden Pass is continuing to carry out Phase I and Phase II activities.

QatarEnergy, ExxonMobil moving forward with Golden Pass LNG work
Train 2 (Image: Golden Pass LNG)

Golden Pass and its contractors progressed installation of piping and steel in process and utilities areas and flare wall modifications, continued piping and vessels insulation activities, while concrete foundation pours continued in Train 2 and Train 3.

In addition, Golden Pass progressed setting various vessels on respective foundations and progressed brownfield tie-ins in Trains 2 and 3, and progressed brownfield tie-ins and LNG tank tops modifications scope.

Golden Pass also progressed cable tray installations and cable pulling activities and continued pipe pneumatic / hydrostatic testing program.

As per the pipeline expansion project, Golden Pass continued civil activities and concrete foundation pours at milepost MP33 and MP69 compressor stations and also continued pipe fabrication and installation at these stations.

It also continued construction activities of the Sabine Spur, Natural Gas Pipeline (NGPL)
Interconnect improvements, and associated facilities.

QatarEnergy, ExxonMobil moving forward with Golden Pass LNG work
Flare area (Image: Golden Pass LNG)

H1 2025

Regarding the start of operations, the FERC said in an inspection report in November that the anticipated timing for the first Golden Pass train is the second half of 2024, with the second and the third train following after.

The anticipated in-service timing for the pipeline expansion project is expected sometime prior to the second half of 2024, it said.

ExxonMobil’s senior VP and CFO, Kathryn Mikellss, recently said that “train 1 mechanical completion is expected at the end of 2024 with first LNG in first half of 2025.”

The US currently exports LNG via Cheniere’s Sabine Pass and Corpus Christi plants, Sempra’s Cameron LNG terminal, Venture Global’s Calcasieu Pass facility, the Freeport LNG terminal, Berkshire Hathaway’s Cove Point terminal, and Kinder Morgan’s Elba Island facility.

Besides the Golden Pass LNG export plant, Venture Global expects to start commissioning its Plaquemines LNG facility this year.

Most Popular

Golar’s fourth unit may be world’s largest FLNG

Golar LNG's next converted FLNG may have a capacity of 5 mtpa, which would make it the world's largest FLNG, according to CEO Karl Staubo.

Sempra eyes Port Arthur LNG expansion FID in 2025

Sempra Infrastructure, a unit of Sempra, expects to make a final investment decision on the second phase of its Port Arthur LNG export project in Texas in 2025.

Venture Global to introduce gas to 9th Plaquemines liquefaction block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the ninth liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

More News Like This

Hanwha Ocean delivers 200th LNG carrier

South Korea's Hanwha Ocean has delivered its 200th liquefied natural gas (LNG) carrier.

Sicim bags Rovuma LNG gig

Italy's Sicim has secured a contract from Subsea 7 for the ExxonMobil-led Rovuma LNG project in Mozambique.

Construction advances on Golden Pass LNG terminal

Energy giants QatarEnergy and ExxonMobil and their contractors continue to move forward with the construction work on the Golden Pass LNG export facility in Texas.

TotalEnergies CEO says partners working hard on Papua LNG

TotalEnergies has a 37.55 percent operating stake in the Papua LNG project, ExxonMobil has 37.04 percent, Santos owns a...