BP hopes to launch Tortue FLNG project in Q1 2024

UK-based energy giant BP is “hopeful” that it will launch the first phase of its Greater Tortue Ahmeyim FLNG project located offshore Mauritania and Senegal in the first quarter of 2024, according to its interim CEO Murray Auchincloss.

BP said in its second-quarter report that the launch of the Tortue FLNG project will be pushed back to the first quarter of 2024, while project partner Kosmos Energy said this is due to a delay in the subsea workstream.

Also, BP recently selected Swiss-based offshore contractor Allseas to complete the remaining subsea pipelay scope for the FLNG project, replacing previous contractor Houston-based McDermott.

“As far as Tortue goes on Phase 1 itself, we’re at about 90 percent complete now. The offshore breakwater and facilities are complete and handed over to operations,” Auchincloss told analysts during BP’s third-quarter earnings call on Tuesday.

He said that BP expects the project’s FLNG to leave Singapore by the end of the year.

Golar LNG said in August that it expected the converted floating LNG producer, Gimi, to leave Seatrium’s yard in Singapore in September and after that it moved the departure to October.

The 2.5 mtpa FLNG was on Wednesday still located at the yard, according to its AIS data.

Gimi will serve BP’s Tortue FLNG project under a 20-year charter deal.

Moreover, the project’s floating production, storage and offloading (FPSO) unit left Cosco Shipping Heavy Industry’s yard in Qidong, China in January this year.

The GTA FPSO was on Wednesday located offshore Maputo, South Africa, its AIS data shows.

“The FPSO has left China and Singapore, and it’s on its way to West Africa,” Auchincloss said.

Following completion of commissioning activities at the site offshore Mauritania and Senegal, the FPSO will process natural gas – removing condensate, water, and other impurities – before exporting it by pipeline to the project’s FLNG facilities, 10km offshore.

With eight processing and production modules, the FPSO will process around 500 million standard cubic feet of gas per day.

The FLNG will liquefy majority of the gas, enabling export to international markets, while some of the supplies will help meet growing demand in the two host countries, BP previously said.

BP still expects to launch Tortue FLNG project in Q1 2024
Gimi (Image: Golar LNG)

Phase 2

Besides the first phase, BP and its partners are also working on the second phase.

In February, BP and partners confirmed the development concept for the second phase of the GTA LNG project.

In addition to Kosmos, other partners include Petrosen and SMH.

The partnership will evaluate a gravity-based structure (GBS) as the basis for the GTA Phase 2 expansion project.

BP said the project will have a total capacity of between 2.5-3 million tonnes per annum.

The concept design will also include new wells and subsea equipment, integrating with and expanding on existing GTA infrastructure.

“As far as Phase 2 goes, we really need to focus right now on getting Phase 1 up, that is the principal focus we have,” Auchincloss said during the call.

“As we do that, we’ll see how the productivity is of the resource base, and that will inform Phase 2, where we have to continue through the design, we’re in to optimize in that space and commercial negotiations with the host governments and partners,” he said.

Most Popular

Cheniere produces first LNG cargo at Corpus Christi expansion project

US LNG exporting giant Cheniere has produced the first cargo at the Corpus Christi Stage 3 expansion project in Texas.

Centrica seals LNG supply deal with Petrobras

UK-based energy firm Centrica has signed a 15-year LNG supply deal with Brazil’s state-owned energy firm Petrobras.

Japan’s Japex boosts LNG sales

Japan Petroleum Exploration (Japex) boosted its sales of liquefied natural gas (LNG) in the April-December period last year.

More News Like This

Venture Global says to launch Calcasieu Pass LNG commercial ops in April

US LNG exporter Venture Global LNG expects to launch commercial operations at its Calcasieu Pass LNG terminal in Louisiana in April, some 68 months from its final investment decision and 38 months after production start.

Chinese yard starts Golar FLNG conversion job

China's CIMC Raffles is about to start converting Golar LNG's 148,000-cbm Moss-type carrier, Fuji LNG, into an MKII FLNG with a capacity of 3.5 mtpa following the arrival of the LNG carrier at the yard.

Golar sells its last LNG carrier

Golar LNG has agreed to sell the last liquefied natural gas carrier in its fleet, completing its transition into a focused FLNG infrastructure firm.

BP chief expects ruling on Venture Global dispute later this year

BP's CEO Murray Auchincloss expects a ruling on an arbitration dispute with US LNG exporter Venture Global LNG to be delivered in the second half of this year.