Dutch Gasunie joins forces with German government to build Brunsbuettel LNG import terminal

Dutch gas grid operator Gasunie is joining forces with the German government and RWE to build the Brunsbuettel LNG import terminal as the country looks to reduce reliance on Russian gas.

In that regard, Gasunie, state-owned Kreditanstalt fur Wiederaufbau (KfW), and German energy firm RWE signed a memorandum of understanding on Friday.

Gasunie, a shareholder in the Dutch Gate facility, said in a statement it would operate the LNG terminal and it plans to start building the plant with an annual capacity of 8 billion cbm this year.

In addition to LNG, the terminal would also be made suitable for importing (green) hydrogen, it said.

Germany’s Ministry for Economic Affairs and Climate said in a separate statement it would take a 50 percent share in the LNG terminal through a financial contribution on behalf of the German government.

Gasunie will have a 40 percent operating stake while RWE will hold 10 percent.

Construction could take up to 3.5 years

The ministry did not reveal any financial details of the deal but it said that the construction of the onshore terminal could take about 3-3.5 years.

However, in the case of an FSRU-based facility, it would take about two years to launch it, the ministry said.

This deal comes just a week after Chancellor Olaf Scholz said Germany had decided to back the construction of two LNG import terminals as part of efforts to reduce dependence on Russian pipeline gas imports.

The facilities include the Brunsbuettel LNG terminal and Uniper’s LNG import and hydrogen facility in Wilhelmshaven.

Uniper previously planned to build the Wilhelmshaven FSRU terminal. The unit of Finland’s Fortum switched plans from LNG to hydrogen last year but the company is now considering to revive the project.

Besides these two projects, Germany’s Hanseatic Energy Hub is also working on the Stade LNG import terminal near Hamburg while Belgium-based Tree Energy Solutions (TES) is looking to import both LNG and hydrogen via a planned hub in the German port of Wilhelmshaven.

Expanding import options

Germany is a major gas importer and gets about 55 percent of these supplies from Russia, followed by Norway with about 30 percent, and the Netherlands with about 13 percent, according to the ministry.

The country currently has no large LNG import terminals.

German Economy Minister Robert Habeck said, “it is absolutely clear that we have to make the energy supply climate-neutral, consistently reduce gas consumption and push ahead with the expansion of renewables and the production of hydrogen at full speed.”

However, he said Germany needs gas for the transition.

“At the same time, it is necessary to reduce dependence on Russian imports as soon as possible. With an LNG terminal in Brunsbuettel, we are expanding the import options,” Habeck said.

Changes at German LNG Terminal

German LNG Terminal, the JV behind the Brunsbuettel LNG project, has been working on the facility since 2018.

The JV consists of Gasunie and Germany’s Oiltanking while Dutch tank firm Vopak decided to become a passive shareholder last year.

RWE previously expressed interest to take a large part of the terminal’s capacity as well as to import hydrogen from Australia to Brunsbuettel.

Following the new deal with the government, Vopak and Oiltanking would leave the group of shareholders ultimately by May 2022, German LNG Terminal said in a statement on Saturday.

“The current shareholders have agreed that Gasunie is the best partner for the German government to complete the terminal project quickly and successfully in order to ensure stable energy supply with gas and enhance security of supply in Germany,” it said.

Also, the former joint managing director Philipp Kroepels will return to Oiltanking while Michael Kleemiß will remain managing director of the JV.

Contractor to start preparatory work

German LNG Terminal submitted its application for planning approval to the Transport Planning Authority in Kiel in Summer 2021.

It would now move ahead at “full speed” with the process, the JV said.

In addition, the EPC contractor consisting of Cobra and Sener would be commissioned to start the preparatory work immediately, German LNG Terminal said.

The project includes a jetty with two berths, with both unloading and loading capabilities, for LNG carriers ranging from 1,000 cbm up to 265,000 cbm.

It will also have two LNG tanks each with a capacity of 165,000 cbm.

Most Popular

Japan’s MOL merges six ship management companies into one entity

Japanese shipping giant MOL, owner of a large LNG carrier fleet, has merged six of its ship management companies...

Top 5 news of the week August 24-30

LNG Prime brings you the five most popular news stories on our platform during the week of August 24-30, 2026.

Germany’s BASF gets first LNG cargo under Cheniere contract

German chemicals giant BASF has received its first liquefied natural gas (LNG) cargo under a long-term contract with US LNG exporter Cheniere.

More News Like This

Gasunie: Dutch gas storage will not meet winter filling target

Dutch gas grid and LNG terminal operator Gasunie said on Wednesday that the Netherlands will not meet its previously set gas storage filling target of 115 TWh for this winter, which is about half of the country's gas consumption.

Woodside: RWE’s deal with Stonepeak has no impact on Louisiana LNG ownership structure

RWE's agreement with US private equity firm Stonepeak has no impact on Louisiana LNG ownership structure, a Woodside spokesperson told LNG Prime.

Gasunie and Vopak to launch fourth Gate LNG tank in Q3

Dutch partners Gasunie and Vopak expect to launch the fourth LNG tank at their Gate terminal in the third quarter of this year, according to Vopak CEO Dick Richelle.

MT Group bags contract for German LNG terminal

Lithuanian EPC contractor MT Group has secured a contract for the German government-backed onshore LNG import terminal in Brunsbuttel.