Estonia’s Alexela and Infortar wrap up Paldiski LNG work

Estonian energy company Alexela and compatriot investment firm Infortar have completed the construction work on the FSRU-based Paldiski LNG import facility.

Alexela said in a social media post that the work on the mooring point was completed on October 28, few days earlier ahead of the promised deadline.

The port will be soon ready to receive LNG carriers, according to Alexela.

“The world record has been achieved and the promise made in the spring has been fulfilled – as far as we know, no one has built an LNG terminal anywhere in the world only in six months,” the company said.

However, Estonia’s gas and electricity transmission system operator, Elering, still needs to complete installation of the gas equipment, including loading arms.

“We want to make sure that the gas equipment by Estonia’s gas and electricity transmission system operator will be installed so the gas reception capacity will be established in Paldiski LNG terminal by the end of this November,” Alexela said.

Elering said in June that construction work had started on the pipeline that will connect the planned FSRU-based LNG import terminal in Paldiski to the grid.

The pipeline will be long about 1.2 kilometers, linking the LNG terminal’s jetty to Elering’s onshore compressor station.

Excelerate’s FSRU to go to Inkoo

As per the FSRU, Estonia and Finland agreed to jointly charter an FSRU to import LNG, as part of plans to reduce reliance on Russian pipeline gas and boost energy security.

After that, Gasgrid signed a 10-year deal to charter one FSRU from US LNG player Excelerate.

Under the charter deal, Excelerate will provide its 150,900-cbm Exemplar which can supply more than 5 billion cubic meters per year of regasification capacity.

Previously, the two countries said that the FSRU would dock either at Inkoo or Paldiski, depending on which facility is completed first.

However, Finland and Estonia recently agreed to place FSRU Exemplar in the Finnish port of Inkoo.

The two countries agreed that the LNG terminal in Inkoo would ensure the gas supply of both Estonia and Finland on equal terms in order to reduce the risks of security of supply in the coming winter, Gasgrid previously said.

Gasgrid said in a update on October 14 that it had completed bored-pile driving work at the Inkoo facility. The port structures are due for completion in December ahead of the arrival of the FSRU, it said.

The Finnish state-owned natural gas transmission system operator is expecting the first commissioning cargo to arrive at the FSRU in December while the commercial operations should start in January 2023.

Most Popular

MAN will no longer offer ME-GA engine

Volkswagen’s MAN unveiled the ME-GA dual-fuel engine in March 2021, describing it as an Otto-cycle variant of the company’s...

Kumul awards pre-FEED contract to Wison for Papua New Guinea’s first FLNG

The two firms signed the contract on Friday. With an expected capacity of 1.5 mtpa, Papua New Guinea’s first FLNG...

Atlantic LNG shipping rates dip to $26,750 per day

Last week, Atlantic LNG shipping rates dropped below $50,000 per day. “Spark30S Atlantic rates dropped for a fourth consecutive week,...

More News Like This

Rohe starts bio-LNG production at Finland’s Hamina terminal

According to statement by Rohe, first supplies of bio-LNG, or liquefied biomethane, were produced on August 29. Rohe announced in...

Gasgrid: Inkoo FSRU capacity 50 percent booked in 2025

In July, Gasgrid's unit Floating LNG Terminal Finland offered in total of 22 terminal slots of 950 GWh each...

Finland’s Gasgrid offers Inkoo FSRU capacity for 2025

A unit of Finland’s Gasgrid is offering regasification capacity for 2025 at the FSRU-based LNG import terminal in Inkoo. According...

Gasgrid: Inkoo FSRU capacity 95 percent booked in 2024

Finland’s gas system and LNG terminal operator Gasgrid said companies have booked 95 percent of the offered regasification capacity...