Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Germany’s first LNG terminal starts supplying gas to grid

Germany’s first FSRU-based import facility in Wilhelmshaven, operated by Uniper, has started supplying regasified LNG to the grid.

The 170,000-cbm FSRU Hoegh Esperanza arrived in Wilhelmshaven on December 15 while Uniper and its partners launched the facility two days later.

Uniper operates the facility on behalf of the German government, Niedersachsen Ports performed the works on the port infrastructure, such as the recently completed jetty, while OGE was responsible for the 26 kilometers long connecting pipeline.

The FSRU stated delivering regasified LNG to the pipeline on Wednesday, one day ahead than Uniper had originally planned, the energy firm said.

Prior to arriving in Wilhelmshaven, the FSRU took a cargo in Spain at the Saggas regasification plant in Sagunto operated by Enagas.

Uniper said the shipment of 165,000 cbm of LNG is enough to supply around 50-80,000 German households for a year.

In future, Hoegh Esperanza would feed at least five bcm of natural gas into the German gas grid each year.

That is around six percent of Germany’s gas demand, and would thus replace around eleven percent of Germany’s gas imports from Russia, Uniper said.

First LNG tanker to dock at the terminal in early January

Uniper expects the first LNG tanker to dock at the FSRU in early January.

The 2016-built 174,000-cbm LNG carrier, Maria Energy, owned by TEN and chartered by Uniper, is on its way to Wilhelmshaven and is expected to arrive there on January 2, according to its AIS data provided by VesselsValue.

Maria Energy previously loaded a cargo at Venture Global LNG’s Calcasieu Pass terminal in Cameron, Louisiana, the data shows.

LNG Prime contacted Uniper for a comment regarding the matter but we did not receive a reply by the time this article was published.

Six FSRU-based terminals

The Wilhelmshaven facility is the first of six FSRU-based terminal in Germany that are expected to go online by the end of 2023.

The government backed the charter of five FSRUs while Deutsche ReGas is developing the first private FSRU-based facility in Lubmin.

Hoegh LNG said earlier on December 15 it signed a binding 10-year time charter contract with the German government for the FSRU Hoegh Esperanza.

The FSRU will be operated by Uniper acting as agent on behalf of the German Federal Ministry for Economic Affairs and Climate Action.

German energy firm RWE is also expecting to receive the first commissioning cargo at the Elbhafen FSRU-based LNG import terminal in Brunsbuettel in January. This terminal will also feature Hoegh’s vessel, Hoegh Gannet.

In addition, Deutsche ReGas last week moved the the 2009-built 145,000-cbm FSRU Neptune from the Mukran Port on the island of Ruegen to Lubmin while it welcomed the FSU as well.

Deutsche ReGas said in a statement on Thursday it had received approval from the European Commission for exemption from regulation for the new floating LNG terminal.

However, the company is still awaiting to receive approval by the local government to launch the facility.

Depending on this, the Lubmin facility would become the second operational terminal in Germany, followed by the Brunsbuettel facility.

The three other FSRU-terminals are expected to go online later in 2023.

Most Popular

Excelerate’s FSRU arrives in Germany

Excelerate’s 138,000-cbm FSRU Excelsior has finally arrived in Germany, where it will start serving DET's second LNG import terminal in Wilhelmshaven.

Woodside assessing tariff impact on Louisiana LNG

Australian LNG player Woodside is assessing the impact of recent US tariffs and other trade measures on its Louisiana LNG project, according to Woodside CEO Meg O’Neill.

Chevron: production at first Wheatstone LNG train reduced due to maintenance

Production at the first liquefaction train of Chevron's Wheatstone LNG plant near Onslow has been reduced due to maintenance, a Chevron Australia spokesperson told LNG Prime on Tuesday.

More News Like This

Excelerate’s FSRU arrives in Germany

Excelerate’s 138,000-cbm FSRU Excelsior has finally arrived in Germany, where it will start serving DET's second LNG import terminal in Wilhelmshaven.

Woodside, Uniper ink Louisiana LNG supply deal

Australia's Woodside has signed LNG sale and purchase agreements with Germany's Uniper to supply the latter from its planned Louisiana LNG project and its global portfolio.

Woodside in LNG supply talks with Germany’s Uniper

Australian LNG player Woodside confirmed on Wendesday it is in talks with Germany's Uniper over a potential LNG supply deal.

Deutsche ReGas: Mukran LNG capacity fully booked in 2025

German LNG terminal operator Deutsche ReGas has allocated all of the available slots at its FSRU-based LNG terminal in Mukran in 2025.