Cheniere expects to complete Corpus Christi LNG expansion ahead of schedule

US LNG exporting giant Cheniere is expecting to complete the expansion phase at its Corpus Christi plant in Texas ahead of schedule, according to the company’s CEO Jack Fusco.

Cheniere’s Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

In June last year, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Deliveries are expected to begin in 2025 with full production in 2027.

Fusco told analysts during Cheniere’s second-quarter earnings call last week that Bechtel “continues to progress Corpus Christi Stage 3 well ahead of schedule, increasing my optimism for that project being completed ahead of the guaranteed date.”

“Certain construction activities on Stage 3 are taking place ahead of plan, and I remain optimistic on schedule outperformance and potentially having more LNG volumes in 2025, and possibly the entire seven-train project complete by the end of 2026,” the CEO said.

Moreover, Fusco said that construction activities continue to ramp up and the project is 38.1 percent complete and there are now 1,000 personnel on site.

“In fact, during the second quarter, the first steel structure was erected, an important milestone for Stage 3,” he said.

He told analysts that on Cheniere’s next quarterly call, the company will provide “a much more fulfilling update on the schedule.”

Most Popular

Venture Global to introduce gas to tenth Plaquemines liquefaction block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the tenth liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

Eni: third phase of YPF’s Argentina LNG project requires $20 billion investment

The third phase of YPF's Argentina LNG export project would require an investment of about $20 billion, according to Eni’s COO of global natural resources, Guido Brusco.

Kimmeridge’s Commonwealth LNG seeks expedited approval from FERC

Kimmeridge's Commonwealth LNG is seeking expedited final approval from the US FERC as it looks to make a final investment decision on its planned LNG export plant in Louisiana later this year.

More News Like This

Cheniere to start site preparation for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere is seeking approval from the US FERC to start site preparation activities for two more midscale trains at its Corpus Christi LNG plant in Texas.

Port of Corpus Christi says Q1 LNG volumes up 12.3 percent

The US Port of Corpus Christi in Texas reported a 12.3 percent year-on-year increase in its liquefied natural gas (LNG) volumes in the first quarter of this year.

Cheniere progresses commissioning of second Corpus Christi expansion train

US LNG exporting giant Cheniere is moving forward with commissioning activities at the second train of the Corpus Christi Stage 3 expansion project in Texas following the substantial completion of the first unit.

Corpus Christi LNG expansion project 80 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 80 percent complete.