Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Cheniere’s Corpus Christi expansion project almost 58 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is almost 58 percent complete, and the US LNG exporting giant is working to start production at the first train later this year.

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and compatriot Bechtel officially started construction on the project in October the same year.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the April construction report filed with the US FERC last month that overall project completion for the Stage 3 project is 57.6 percent.

The project was 55.9 percent complete as of March 31, 2024.

Stage 3 engineering and procurement are 90.5 percent and 75.2 percent complete, respectively, while subcontract and direct hire construction work are 79.4 percent and 19.3 percent complete, respectively.

Work continues to progress

During the month of April, CCL’s contractor continued piling activities, road improvements, drainage work and mobilization of temporary facilities, equipment, and personnel, it said.

Moreover, piling activities continued in train 7, and OSBL and are anticipated to conclude in May.

Concrete work continues in trains 2, 3, 4, 5 and OSBL, while structural steel continues in trains 2, 3 and OSBL.

Underground piping is progressing in train 1, 2, 3, and OSBL and has started in train 4.

Aboveground piping is progressing in train 1, train 2 and OSBL West.

CCL said equipment setting is ongoing in trains 1, 2, and 3.

The FERC also said in a separate filling it has granted CCL’s request to energize the train 1 substations.

First LNG production by end of 2024

Cheniere initially said that LNG deliveries from the expansion project were expected to begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

The company confirmed in its first quarter report that it expects to achieve first LNG production from the first train at the end of 2024.

Substantial completion of the project is expected during 1H 2025 – 2H 2026.

Besides this expansion, Cheniere plans to build two more liquefaction trains as part of the third expansion phase at the Corpus Christi plant.

In addition, Cheniere also aims to build two new liquefaction trains as part of the Sabine Pass Stage 5 expansion project to add up to 20 mtpa of capacity to the giant 30 mtpa facility.

Most Popular

Excelerate buys NFE’s Jamaica business for $1.05 billion

US FSRU player Excelerate Energy has entered into a definitive agreement with compatriot LNG player New Fortress Energy to acquire NFE’s business in Jamaica for $1.055 billion in cash.

Snam’s Ravenna FSRU to get first LNG shipment

Snam's 170,000-cbm FSRU BW Singapore, located off Italy's Ravenna, is set to receive the first LNG cargo from the US as part of its commissioning activities.

Argentina’s Enarsa gets offers for LNG cargo tender

Argentina's state-owned LNG importer Energia Argentina (Enarsa) has received seven offers for its first LNG cargo tender in 2025.

More News Like This

Cheniere ships 4,000th LNG cargo

US LNG exporting giant Cheniere has produced and exported the 4,000th cargo of liquefied natural gas from its Sabine Pass and Corpus Christi terminals since 2016.

Cheniere completes first train at Corpus Christi expansion project

US LNG exporting giant Cheniere has achieved substantial completion of the first liquefaction train at the Corpus Christi Stage 3 expansion project in Texas.

Cheniere gets FERC OK for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere has received approval from the US FERC to build two more midscale trains at its Corpus Christi LNG plant in Texas.

Corpus Christi LNG expansion project 78.3 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 78.3 percent complete.