Cheniere’s third Sabine Pass jetty 96.4 percent complete

US engineer Bechtel has completed 96.4 percent of the third jetty project at Cheniere’s six-train 30 mtpa Sabine Pass LNG facility in Louisiana.

According to the latest construction update filed with FERC, the project was 96.4 percent complete as of July this year, against the plan of 97.2 percent.

Cheniere said in the update that engineering was 100 percent complete, procurement 100 percent, subcontracts 99.4 percent, while construction was 89.9 percent complete.

During the month of July, construction completed excavations for the LNG swale, vendor steel installations on the PND (tug berth) wall, and cleaning of piping lines, according to Cheniere.

Nine systems were turned over to commissioning and startup (CSU) in July, and the last hydrocarbon systems would be turned over at the beginning of August, the LNG producer said.

Also, the remaining systems would be turned over throughout the month, with the respective commissioning demonstration tests closely following, it said.

Cheniere is adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

It will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at the plant by 180 per year.

Cheniere said earlier this year that operations of the jetty could start by the end of 2022.

Besides the Sabine Pass plant, Cheniere recently took a final investment decision on Stage 3 expansion at its Corpus Christi LNG export plant in Texas.

The expansion will add about 10 mtpa to the three-train 15 mtpa Corpus Christi plant.

In addition, Cheniere’s CEO Jack Fusco recently said the company was working to add over 30 million tonnes of capacity at its Sabine Pass and Corpus Christi plants.

Most Popular

CEO: Venture Global to sign multiple 20-year LNG contracts in coming quarters

US LNG exporter Venture Global LNG expects to sign and report on multiple 20-year LNG supply contracts in the incoming quarters, according to CEO Mike Sabel.

Woodside’s Louisiana LNG seeks FERC extension

Woodside is seeking an additional eight-month extension from the US FERC to complete and put into service its Louisiana LNG export facility.

Venture Global reveals LNG fleet details

US LNG exporter Venture Global LNG has revealed more details regarding its fleet of nine owned and three chartered liquefied natural gas carriers.

More News Like This

Cheniere nears first LNG at second Corpus Christi expansion train

Cheniere's CEO, Jack Fusco, expects the company to achieve first LNG at the second train of the Corpus Christi Stage 3 expansion project in Texas later this month or at the beginning of June.

Cheniere reports higher Q1 revenue

US LNG exporting giant Cheniere reported a rise in its quarterly revenue due to higher prices, while its net profit decreased compared to the same period last year.

Cheniere to introduce fuel gas to second Corpus Christi LNG expansion train

US LNG exporter Cheniere is nearing the introduction of fuel gas to the second train of the Corpus Christi Stage 3 expansion project in Texas as part of the commissioning phase.

Cheniere’s Corpus Christi expansion project 82.5 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 82.5 percent complete.