Construction progresses on Golden Pass LNG export terminal

QatarEnergy and ExxonMobil are moving forward with the construction work on their $10 billion Golden Pass LNG export terminal in order to launch the facility in 2024.

State-owned LNG giant QatarEnergy owns a 70 percent stake in the project while US energy firm ExxonMobil has a 30 percent share.

Once complete, the giant facility, located next to the existing LNG import terminal in Sabine Pass, will have three trains and a total liquefaction capacity of about 16 mtpa.

Last month marked the safe arrival and installation of the project’s first main cryogenic heat exchanger, Golden Pass LNG said in a social media post on Thursday.

US LNG equipment specialist Air Products said in February it had completed the largest heat exchanger for the Golden Pass LNG export project.

Air Products built the heat exchanger that weighs nearly one million pounds at its facility in Port Manatee, Florida.

Back in February 2019, the US firm secured a contract from the Golden Pass JV to provide its proprietary LNG technology, equipment, and related process license.

The scope of supply includes its AP-C3MRTM natural gas liquefaction technology and equipment, and three of its MCR main cryogenic heat exchangers.

Other activities

Besides the heat exchanger, construction continues to progress across the LNG plant’s site.

“Golden Pass is continuing to carry out Phase I and Phase II activities, such as storm water
protection, levee construction, stockpiling of material, and piling,” the JV said in its latest monthly update sent to FERC.

In addition, the company has progressed structural steel erection and piping installation in the main pipe racks for the first train and utilities.

It has also progressed trains and utilities foundation and underground piping installation, helical piling program, and continued to set various vessels on respective foundations, the update said.

Most Popular

Venture Global seals new deals to support expansion of its power network

US LNG exporter Venture Global has entered into power and grid frame agreements with GE Vernova and Baker Hughes for up to 16 new, 720 MW power island units and associated power transformer equipment, supporting the continued expansion of its existing behind-the-meter, industrial power network that is not reliant on the grid.

Venture Global gets approval to place first Plaquemines LNG phase in service

Venture Global’s Plaquemines LNG has secured approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.

Hanwha Ocean, Posco plan to build LNG carrier with high-manganese steel tanks

South Korean shipbuilder Hanwha Ocean and steel producer Posco plan to build a liquefied natural gas (LNG) carrier equipped with high-manganese steel cargo tanks.

More News Like This

MISC names QatarEnergy LNG carrier

South Korea's Samsung Heavy Industries hosted a naming ceremony for a liquefied natural gas (LNG) carrier it built for Malaysia's MISC and state-owned LNG giant QatarEnergy.

Edison says QatarEnergy extends force majeure until early December

Italian energy firm Edison, a unit of EDF, said it received a new force majeure notification from state-owned LNG giant QatarEnergy, affecting supplies scheduled for delivery at the Adriatic LNG terminal in Italy until the beginning of December.

ExxonMobil’s Rovuma LNG seeks contractor for land transportation services

US energy giant ExxonMobil and its partners in the planned Rovuma LNG project in Mozambique have invited companies to submit expressions of interest to provide land transportation services.

ExxonMobil’s PNG LNG hits production milestone

The ExxonMobil-operated PNG LNG project in Papua New Guinea has reached a new milestone, producing more than 100 million tons of liquefied natural gas (LNG) since operations began in 2014.