Croatia to launch Krk terminal with US LNG?

Croatia’s long-awaited LNG import terminal on the island of Krk in the northern Adriatic Sea could receive its first commercial cargo from the US.

The BP-chartered 155,000-cbm Tristar Ruby left the Dominion Cove Point facility in Maryland on Saturday and its AIS data shows that it would arrive at the Krk facility on January 1.

LNG Croatia, the state-owned Krk terminal developer previously said it planned to start commercial operations on January 1.

To remind, Croatia’s first FSRU arrived at the facility earlier this month after picking up a small commissioning cargo from Sagunto in Spain.

Besides the FSRU, the import facility consists of a jetty and a high-pressure gas pipeline.

Croatia’s first LNG terminal will have a capacity to send up to 2.6 bcm per year of natural gas into the national grid.

Furthermore, the terminal developer said earlier this year that three firms booked all of the terminal’s capacities for the next three years.

The capacity takers include Hungary’s state-owned MFGK and trading firm MET.

Additionally, Hungary said in September the country signed a deal with LNG giant Shell to receive natural gas via the Krk facility as part of the MFGK booking.

Qatar’s PowerGlobe, the energy arm of privately-held Optimized Holding, booked the largest capacity at Krk spanning a period of 15 years.

Croatia’s LNG import project costs 233.6 million euros ($286 million) with EU providing 101.4 million euros from the Connecting Europe Facility.

Most Popular

Shell adds another LNG carrier to its fleet

A unit of UK-based LNG giant Shell has added another chartered liquefied natural gas carrier to its fleet.

Chevron, China’s ENN seal second LNG SPA

US energy giant Chevron has signed a second LNG sales and purchase agreement with Chinese independent gas distributor ENN.

Venture Global gets OK to introduce gas to final Plaquemines LNG block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the 18th and final liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

More News Like This

Croatian FSRU heads to Turkish yard to add regas module

The 140,000-cbm FSRU LNG Croatia has left its Krk base and is on its way to Türkiye’s Kuzey Star yard to receive an additional regasification module.

Croatian FSRU gets Trinidad LNG cargo

Croatia’s FSRU-based LNG terminal on the island of Krk has received a cargo of liquefied natural gas from Trinidad and Tobago's Atlantic LNG plant, according to shipping data.

Croatia’s HEP launches LNG cargo tender

Croatian state-owned power utility HEP is seeking up to six LNG cargoes for delivery to the FSRU-based LNG terminal on the island of Krk.

Croatian FSRU welcomes first Moss-type LNG carrier

Croatia’s FSRU-based LNG terminal on the island of Krk has welcomed the first Moss-type LNG carrier and its 118th cargo since the launch of operations in January 2021.